Robex Resources Advances Kiniero Gold Project Toward Production

Robex Moves Forward with Kiniero Gold Project Construction
Robex Resources Inc. is making significant strides at its Kiniero Gold Project, maintaining both schedule and budget as it gears up for the first gold pour anticipated in the fourth quarter of the calendar year 2025. This project has not only demonstrated a dedicated push towards completion but has also maintained a strong safety record, marking over 3.9 million hours of work since January 2023 without a lost time injury (LTI).
Construction Progress Update
As of the latest updates, various aspects of the construction at Kiniero are moving along swiftly. The process plant and power station concrete works are nearing completion, with significant infrastructure already in place. A key highlight is the completion of the CIL (Carbon in Leach) tank trains and the successful installation of intertank launders. The overall erection of field tanks stands at 83% completion, showcasing the solid commitment to the project's timeline.
Engineering Works Achievements
The Structural, Mechanical, and Piping (SMP) works are progressing steadily, currently reported at 22% completion. This segment of work is crucial as it includes erecting essential components needed for the processing phase of the gold extraction. Additionally, the construction of the tailings storage facility's main eastern embankment continues to take shape, reflecting Robex’s commitment to sustainable mining practices.
Drilling and Exploration Activities
Drilling activities at the Sabali pit are showing encouraging progress, with 35,518 meters drilled in July alone. The company is currently awaiting the analysis results for over 32,000 samples, which are expected to provide insightful data on the mining operations' future.
Operational Readiness and Next Steps
Moving forward, Robex is focusing on crucial next steps in the construction timeline. This includes the ongoing installation of steelwork within the process plant and the mechanical assembly of equipment as it arrives on-site. The mill installation is on a parallel path, with teams mobilizing mid-August for concurrent work on both SAG and Ball mills.
Future Plans for Optimization
In terms of operational efficiency, the company plans to award contracts for laboratory operations and power station maintenance very soon. There is also an emphasis on solar energy integration, as Robex is working towards finalizing an agreement for the supply, installation, and operation of a solar PV plant. This is aligned with their goal to foster environmentally responsible mining.
Commitment to Safety and Efficiency
Throughout the construction phases, Robex is ensuring that all safety protocols are adhered to rigorously. The ongoing mobilization of mining services contractors has seen 70% of the Tranche 1 equipment delivered to the site. This careful planning and execution are indicative of the company’s aim to stay on schedule and maintain efficient operations.
Robex's Vision
Robex’s Managing Director and CEO, Matthew Wilcox, expresses satisfaction with the project’s progress, emphasizing the team's unwavering commitment. He noted, “As we enter the final months of construction, the team is focused and increasingly productive, ensuring that we are on course for our target of first gold in Q4.”
Frequently Asked Questions
1. What is the current status of the Kiniero Gold Project?
The Kiniero Gold Project is on schedule, with the first gold pour expected in Q4 CY25, supported by strong construction and safety records.
2. How many hours of work have been completed without injury?
Since January 2023, Robex has celebrated over 3.9 million hours of work without a lost time injury, demonstrating a strong commitment to safety.
3. What drilling progress has been made?
Over 35,000 meters have been drilled in the Sabali pit recently, with results pending analysis for future evaluations.
4. How is Robex ensuring environmental responsibility?
Robex plans to integrate solar energy into operations by finalizing a contract for a solar PV plant, enhancing sustainability efforts.
5. Who are the key contacts for investors and media?
Investors can reach out to Nathan Ryan from NWR Communications, and emails are available for direct inquiries regarding operations and investor relations.
About The Author
Contact Henry Turner privately here. Or send an email with ATTN: Henry Turner as the subject to contact@investorshangout.com.
About Investors Hangout
Investors Hangout is a leading online stock forum for financial discussion and learning, offering a wide range of free tools and resources. It draws in traders of all levels, who exchange market knowledge, investigate trading tactics, and keep an eye on industry developments in real time. Featuring financial articles, stock message boards, quotes, charts, company profiles, and live news updates. Through cooperative learning and a wealth of informational resources, it helps users from novices creating their first portfolios to experts honing their techniques. Join Investors Hangout today: https://investorshangout.com/
The content of this article is based on factual, publicly available information and does not represent legal, financial, or investment advice. Investors Hangout does not offer financial advice, and the author is not a licensed financial advisor. Consult a qualified advisor before making any financial or investment decisions based on this article. This article should not be considered advice to purchase, sell, or hold any securities or other investments. If any of the material provided here is inaccurate, please contact us for corrections.