follows p.f43 of 10k =part of work extension permi
Post# of 1012
Number Activity description Execution by:
1 Submission of seismic survey plan to the Commissioner and execution of an agreement with a contractor to perform 30 April 2019
2 Commence 3D seismic survey in an area of approximately 50 square kilometers 1 August 2019
3 Transfer of field material configuration and processed material to the Ministry pursuant to Ministry guidelines 15 December 2019
4 Submit interpretation report 20 February 2020