Just wanted to post the real rules for the permit issue on Mitchell #5.The posters on Ihub are editing for there view point
(1) Filing requirements. If a permit to drill requires an exception to the applicable density provision, the operator must file, in addition to the items required by subsection (g) of this section:
(A) a list of the names and addresses of all affected persons. For the purpose of giving notice of application, the Commission presumes that affected persons include the operators and unleased mineral interest owners of all adjacent offset tracts, and the operators and unleased mineral interest owners of all tracts nearer to the proposed well than the prescribed minimum lease-line spacing distance. The Commission designee may determine that such a person is not affected only upon written request and a showing by the applicant that:
(i) competent, convincing geological or engineering data indicate that drainage of hydrocarbons from the particular tracts subject to the request will not occur due to production from the proposed well; and
(ii) notice to the particular operators and unleased mineral interest owners would be unduly burdensome or expensive;
( engineering and/or geological data, including a written explanation of each exhibit, showing that the drilling of a well on substandard acreage is necessary to prevent waste or to prevent the confiscation of property;
(C) additional data requested by the Commission designee.
(2) Notice of application. Upon receipt of a complete application, the Commission will give notice of the application by mail to all affected persons for whom signed waivers have not been submitted.
(3) Approval without hearing. If the Commission designee determines, based on the data submitted, that a permit requiring an exception to the applicable density provision is justified according to subsection (f) of this section, then the Commission designee may issue the exception permit administratively if:
(A) signed waivers from all affected persons were submitted with the application; or
( notice of application was given in accordance with paragraph (2) of this subsection and no protest was filed within 21 days of the notice; or
(C) no person appeared to protest the application at a hearing scheduled pursuant to paragraph (4)(A) of this subsection.
(4) Hearing on the application.
(A) If a written protest is filed within 21 days after the notice of application is given in accordance with paragraph (2) of this subsection, the application will be set for hearing.
( If the application is not protested and the Commission designee determines that a permit requiring an exception to the applicable density provision is not justified according to subsection (f) of this section, the operator may request a hearing to consider the application.
(i) Duration. A permit is issued as an exception to the applicable density provision shall expire two years from the effective date of the permit; unless drilling operations are commenced in good faith within the two year period.
(1) Filing requirements. If a permit to drill requires an exception to the applicable density provision, the operator must file, in addition to the items required by subsection (g) of this section:
(A) a list of the names and addresses of all affected persons. For the purpose of giving notice of application, the Commission presumes that affected persons include the operators and unleased mineral interest owners of all adjacent offset tracts, and the operators and unleased mineral interest owners of all tracts nearer to the proposed well than the prescribed minimum lease-line spacing distance. The Commission designee may determine that such a person is not affected only upon written request and a showing by the applicant that:
(i) competent, convincing geological or engineering data indicate that drainage of hydrocarbons from the particular tracts subject to the request will not occur due to production from the proposed well; and
(ii) notice to the particular operators and unleased mineral interest owners would be unduly burdensome or expensive;
( engineering and/or geological data, including a written explanation of each exhibit, showing that the drilling of a well on substandard acreage is necessary to prevent waste or to prevent the confiscation of property;
(C) additional data requested by the Commission designee.
(2) Notice of application. Upon receipt of a complete application, the Commission will give notice of the application by mail to all affected persons for whom signed waivers have not been submitted.
(3) Approval without hearing. If the Commission designee determines, based on the data submitted, that a permit requiring an exception to the applicable density provision is justified according to subsection (f) of this section, then the Commission designee may issue the exception permit administratively if:
(A) signed waivers from all affected persons were submitted with the application; or
( notice of application was given in accordance with paragraph (2) of this subsection and no protest was filed within 21 days of the notice; or
(C) no person appeared to protest the application at a hearing scheduled pursuant to paragraph (4)(A) of this subsection.
(4) Hearing on the application.
(A) If a written protest is filed within 21 days after the notice of application is given in accordance with paragraph (2) of this subsection, the application will be set for hearing.
( If the application is not protested and the Commission designee determines that a permit requiring an exception to the applicable density provision is not justified according to subsection (f) of this section, the operator may request a hearing to consider the application.
(i) Duration. A permit is issued as an exception to the applicable density provision shall expire two years from the effective date of the permit; unless drilling operations are commenced in good faith within the two year period.