Kenmare Resources Enhances Wet Concentrator Plant A Capabilities

Update on Kenmare Resources’ Wet Concentrator Plant A
Kenmare Resources plc, recognized as a leading producer of titanium minerals and zircon, operates the Moma Titanium Minerals Mine, a significant site for titanium extraction. Recently, the company released an exciting update concerning the upgrade of its Wet Concentrator Plant (WCP) A. This improvement project is pivotal as it gears the plant for the transition to the Nataka ore zone, which is crucial for the future of Kenmare’s operations.
Key Developments Regarding the Upgrade
Ben Baxter, the Chief Operations Officer of Kenmare, shared promising news regarding the progress of the WCP A. According to Baxter, the recent installation of two new dredges and a feed preparation unit was accomplished smoothly, with the commissioning process initiating as of October 2. The company expects a ramp-up in production through the fourth quarter, with ongoing adjustments to achieve full operational capacity.
Baxter commented on the project saying, “The production pause fell within our anticipated schedule of three to four weeks, which we have factored into our production forecasts for 2025. Our team excelled in executing this comprehensive upgrade while upholding an outstanding safety record.”
About the Transition to Nataka
The Nataka ore zone is the most prominent in Moma’s resources, representing about 70% of its total mineral assets. This transition is not just about increased output; it symbolizes a strategic move set to secure Kenmare's production necessities for over two decades. Enhanced mining techniques have been implemented in WCP A to suit the unique conditions of Nataka, which features high levels of slimes that can deter efficient recovery rates. The Plant is strategically upgraded with two high-capacity dredges and a dedicated feed preparation module to manage these challenges effectively.
Investment Insights
The overhaul of WCP A comes with a capital investment of $341 million. This encompasses the establishment of a new Tailings Storage Facility and additional infrastructure that will enable mining operations within the Nataka ore zone.
Looking Ahead: Production Milestones
With the commissioning of WCP A having started, Kenmare anticipates that the plant will achieve its nameplate capacity of 3,500 tonnes per hour by the end of 2025. Operations in the Namalope area are projected to wrap up in the second quarter of 2026, at which point the transition to Nataka will commence and last about 18 months.
Kenmare is set to provide further updates regarding their production outlook on the 15th of October 2025, shedding light on the company's performance and operational adjustments.
Contact Information
For inquiries regarding the WCP A project or any investor-related questions, individuals can reach out to Kenmare Resources directly:
Kenmare Resources plc
Katharine Sutton
Investor Relations
ir@kenmareresources.com
Tel: +353 1 671 0411
Mob: +353 87 663 0875
About Kenmare Resources plc
Kenmare Resources plc stands as one of the leading global producers of titanium minerals, with substantial operations at the Moma Titanium Minerals Mine in Mozambique. With a product line that contributes approximately 6% to the worldwide supply of titanium feedstocks, Kenmare serves clients across over 15 countries worldwide. The company’s minerals are essential components of various consumer products, ranging from paints to plastics and ceramic goods.
Frequently Asked Questions
What is the main focus of Kenmare Resources' recent update?
The update primarily highlights the advancements in the Wet Concentrator Plant A project and its transition to the Nataka ore zone.
How significant is the Nataka ore zone for Kenmare Resources?
The Nataka ore zone represents about 70% of Kenmare's mineral resources, critical for ensuring sustainable production for the company.
What investments were made in the WCP A upgrade project?
The total investment in the WCP A upgrade is reported to be $341 million, including new infrastructure and facilities.
When is the expected ramp-up in production for WCP A?
Kenmare expects the ramp-up to production capabilities by the end of 2025, looking forward to reaching full capacity.
How can investors contact Kenmare Resources for more information?
Investors can contact Katharine Sutton at Kenmare Resources through the provided email or phone numbers for inquiries related to investor relations.
About The Author
Contact Owen Jenkins privately here. Or send an email with ATTN: Owen Jenkins as the subject to contact@investorshangout.com.
About Investors Hangout
Investors Hangout is a leading online stock forum for financial discussion and learning, offering a wide range of free tools and resources. It draws in traders of all levels, who exchange market knowledge, investigate trading tactics, and keep an eye on industry developments in real time. Featuring financial articles, stock message boards, quotes, charts, company profiles, and live news updates. Through cooperative learning and a wealth of informational resources, it helps users from novices creating their first portfolios to experts honing their techniques. Join Investors Hangout today: https://investorshangout.com/
The content of this article is based on factual, publicly available information and does not represent legal, financial, or investment advice. Investors Hangout does not offer financial advice, and the author is not a licensed financial advisor. Consult a qualified advisor before making any financial or investment decisions based on this article. This article should not be considered advice to purchase, sell, or hold any securities or other investments. If any of the material provided here is inaccurate, please contact us for corrections.