Robex's Kiniero Gold Project Progressing Towards 2025 Milestone

Robex Resources Inc. Updates on Kiniero Gold Project
Robex Resources Inc. is making strides toward its gold production goals at the Kiniero Gold Project. Currently scheduled for its first gold pour in Q4 2025, the project is moving steadily, on both time and budget. The construction of the site is proceeding without any lost-time injuries, showcasing the company's commitment to safety throughout the process.
Current Project Status
The project has seen significant advances in various areas. Engineering and design work is fully completed, allowing construction efforts to progress seamlessly. The ongoing phase of grade control drilling at the Mansounia pit has reached an impressive 55,430 meters, with 61,520 samples collected. This drilling is expected to wrap up soon, transitioning efforts toward the Sabali pit.
Key Construction Highlights
- The structural, mechanical, and piping (SMP) work has begun, with 115 tonnes of materials already erected within the milling building.
- All mechanical and electrical equipment procurement is in the final stages, with 90% of power station materials already collected and shipped.
- Concrete works for the process plant are approximately 95% complete, while power station concrete work is 32% done.
- Fabrication of structural steel and platework is ahead of schedule, with respective rates of 89% and 90% completion.
- The CIL tank structure is progressing well, with one tank segment completed, and it's expected the second will wrap up by mid-July 2025.
- There's considerable progress on the tailings storage facility where the base preparation is nearing completion, with more than 625,000 square meters of the liner already placed.
Next Steps for Kiniero
Looking forward, Robex is set to accomplish several milestones in the coming months:
- The completion of the final two concrete pours for the process plant is slated for the end of June 2025.
- All necessary contracts for mining operations will be finalized this month, alongside mobilization efforts already underway.
- Initial stages of mill installation works will start immediately, progressing swiftly into grade control drilling at the Sabali pit.
- Other key tasks include the continuation of steelwork erection within the process plant and beginning overland piping installations.
Commitment to Shareholder Value
Robex’s Managing Director and CEO, Matthew Wilcox, expressed enthusiasm regarding the ongoing work at Kiniero, emphasizing the methodical approach to construction. With the company successfully raising A$120 million through an Initial Public Offer and recent listings on the ASX, the focus remains on delivering shareholder value through both Kiniero and Nampala projects.
Conclusion: A Bright Future Ahead
With all the moving parts on track, Robex Resources Inc. stands well-positioned for success at Kiniero. The positive momentum in construction and planning indicates that the goal of first gold production by Q4 2025 is within reach. Investors and stakeholders can look forward to ongoing updates as the project continues its development path.
Frequently Asked Questions
What is the current status of the Kiniero Gold Project?
The Kiniero Gold Project is progressing well, with construction on schedule for first gold production expected in Q4 2025.
What has been achieved in terms of construction?
The project has reached 95% completion on process plant concrete and is ahead of schedule for structural steel and platework fabrication.
What are the upcoming milestones for Kiniero?
Major concrete pours are expected to complete by the end of June 2025, along with the commencement of mill installation and further drilling operations.
Who is leading the project at Robex?
Matthew Wilcox, the Managing Director and CEO, is overseeing the efforts, pledging to deliver results efficiently while focusing on safety.
How is Robex ensuring safety at the construction site?
Robex has maintained a focus on safety, currently with no recorded lost-time injuries, ensuring a safe working environment during the project execution.
About The Author
Contact Thomas Cooper privately here. Or send an email with ATTN: Thomas Cooper as the subject to contact@investorshangout.com.
About Investors Hangout
Investors Hangout is a leading online stock forum for financial discussion and learning, offering a wide range of free tools and resources. It draws in traders of all levels, who exchange market knowledge, investigate trading tactics, and keep an eye on industry developments in real time. Featuring financial articles, stock message boards, quotes, charts, company profiles, and live news updates. Through cooperative learning and a wealth of informational resources, it helps users from novices creating their first portfolios to experts honing their techniques. Join Investors Hangout today: https://investorshangout.com/
The content of this article is based on factual, publicly available information and does not represent legal, financial, or investment advice. Investors Hangout does not offer financial advice, and the author is not a licensed financial advisor. Consult a qualified advisor before making any financial or investment decisions based on this article. This article should not be considered advice to purchase, sell, or hold any securities or other investments. If any of the material provided here is inaccurate, please contact us for corrections.