Robex Advances Towards Gold Production at Kiniero Project
Robex Resources Inc. is making significant strides towards the production of gold at its Kiniero Gold Project. With the initial gold pour anticipated in Q4 CY25, the project is developing well, reflecting the company's commitment to maintaining schedules and budgets.
Current Status of Kiniero Gold Project
As Robex navigates through construction at Kiniero, several key achievements bolster confidence in its timeline. Notably, the project has recorded over 3.6 million hours worked without a lost time injury, showcasing a strong safety culture amidst the ongoing construction efforts.
Construction Progress
The construction activities are progressing smoothly, with major concrete works almost complete. Reports indicate that approximately 97% of the process plant's concrete work is finalized. Alongside this, the installation of the mill is underway, with baseplates properly aligned and progress being made on the SAG mill shell.
Drilling and Geotechnical Work
In terms of grade control drilling, the first phase at Mansounia has been successfully completed. Meanwhile, drilling continues at Sabali pit with almost 17,000 meters drilled so far. The expectation of high-grade results adds to the positive outlook for the project's mineral assets.
Infrastructure Development at Kiniero
Robex has been strengthening the infrastructure essential for mining operations. The tailings facility's first phase has seen the completion of liner installations, which is critical for environmental management. The team has also signed contracts for mining, ensuring that necessary equipment can mobilize to the site promptly.
Next Steps for the Project
Looking ahead, Robex is committed to operational efficiencies. The completion of the power station concrete and the erection of key mill components will be prioritized. Furthermore, continued drilling at the Sabali pit, awarding haulage contracts, and ensuring readiness for laboratory operations are essential steps in the upcoming months.
Leadership Insights
Matthew Wilcox, the Managing Director and CEO, expressed enthusiasm regarding the project’s progress. He highlighted the remarkable dedication and professionalism of the team in advancing the Kiniero project.
Frequently Asked Questions
What is Robex Resources Inc. currently focusing on?
Robex is focusing on completing the construction of the Kiniero Gold Project with targets set for initial production in Q4 CY25.
How is Robex ensuring safety on the Kiniero project site?
Robex has maintained a strong safety record, working over 3.6 million hours without a lost time injury.
What are the significant milestones achieved in the construction?
Key milestones include the completion of major concrete works, progress in mill installation, and successful grade control drilling.
What drilling activities are currently taking place?
Phase 1 drilling at Mansounia is complete, while drilling at Sabali pit is ongoing, with nearly 17,000 meters completed.
How does Robex plan to move forward in the coming months?
Next steps include finalizing concrete work, erecting mill components, and continuing mining preparations to keep the project on schedule.