Commerce Resources Corp. (CMRZF: OTCQX International) | Commerce Resources Corp. Announces Mineral Resource Update for Upper Fir Tantalum and Niobium Deposit, Blue River, British Columbia Commerce Resources Corp. Announces Mineral Resource Update for Upper Fir Tantalum and Niobium Deposit, Blue River, British Columbia

Commerce Resources Corp. Announces Mineral Resource Update for Upper Fir Tantalum and Niobium Deposit, Blue River, British Columbia

PR Newswire

Highlights

  • Study results show Indicated Mineral Resources totalling 48.4 million tonnes at 197 ppm Ta 2 O 5 and 1,610 ppm Nb 2 O 5 and Inferred Mineral Resources totalling 5.4 million tonnes at 191 ppm Ta 2 O 5 and 1,760 ppm Nb 2 O 5 .

  • Changes result from improved geological interpretation of the mineralized carbonatite host, the grade distribution found in 2011 infill diamond drilling and the increase in Ta metal price over time.

  • Approximately 90% of the tantalum and niobium reside in Indicated resource category.

  • AMEC's "Blue River Tantalum-Niobium Project, British Columbia, Canada , NI 43-101 Technical Report on Mineral Resource Update", with an effective date of June 21, 2013 , will be filed for public disclosure ( www.SEDAR.com ) within 45 days following this news release.

  • With the significant milestone of this resource update successfully achieved, AMEC has recommended a $13.9M program to support a pre-feasibility level study on the Upper Fir deposit.

VANCOUVER , July 12, 2013 /PRNewswire/ - Commerce Resources Corp. (TSXv: CCE; FSE: D7H; OTCQX: CMRZF) has delineated a significant Ta- and Nb-rich carbonatite deposit near the community of Blue River in central eastern British Columbia , and is pleased to announce the completion of a National Instrument (NI) 43-101 compliant Mineral Resource update that incorporates drilling and other exploration results to the end of 2012 for the Upper Fir Tantalum-Niobium Deposit.  A technical report prepared by independent consultants, AMEC Americas Limited ("AMEC") supports the findings of the Mineral Resource update and also includes summaries from a Preliminary Economic Assessment ("PEA") study completed on the Blue River Project and reported in an NI 43-101 compliant Technical Report with an effective date of September 29, 2011 (2011 PEA- see Commerce news release dated November 3, 2011).   The results from the 2011 PEA have not changed in terms of their outcomes as their underlying assumptions remain reasonable.

AMEC constructed the updated carbonatite hosted resource model using a total of 271 holes comprising 59,110m of HQ diameter core and 15,512 samples.  Most holes were at a nominal spacing of 50m with dips typically between -60 degrees to sub-vertical.  The composite body extends more than 1,450m in a north-south direction and as much as 800m in an east-west direction. Tantalum and niobium are contained in the minerals ferrocolumbite and pyrochlore.

The 2011 PEA was developed assuming a sub-level open stoping method with no backfill and no pillar recovery using a processing rate of 7,500 tonnes per day for the Mineral Resource estimation and conceptual design of an underground mine for the Blue River Project. A mineral processing method using a standard-grind flotation process to make a concentrate of ferrocolumbite-pyrochlore was assumed for the Upper Fir material using a proposed process similar to that being used commercially at Iamgold's Niobec Mine in Quebec . The concentrate would be further processed to produce marketable separate oxides of tantalum and niobium. The proposed processes are mature and already in use industrially.

Mineral Resource Statement
The Mineral Resource update is summarized in Table 1.

Table 1:  Blue River Project Estimated Mineral Resource: Effective Date 21 June 2013 , Tomasz Postolski , P.Eng, Qualified Person

                                                 
Ta price
[US$/kg]
      Confidence
Category
      Tonnes       Ta 2 O 5
[ppm]
      Nb 2 O 5
[ppm]
      Contained
Ta 2 O 5
[1000s of kg]
      Contained
Nb 2 O 5
[1000s of kg]
381       Indicated       48,410,000       197       1,610       9,560       77,810
        Inferred       5,400,000       191       1,760       1,000       9,600

Notes:

  1. Assumptions include commodity prices of US$381 /kg Ta, US$46 /kg  Nb,  process recoveries of 65.4% for Ta 2 O 5 and 68.2% for Nb 2 O 5 , US$27 /tonne bulk mining cost and US$48 /tonne selective mining cost, US$15 /tonne process and refining cost, US$3 /tonne G&A cost.
  2. Mineral resources are amenable to underground mining methods and have been constrained using a "Stope Analyzer".
  3. An economic cut-off was based on the estimated operating costs assuming either the bulk or selective mining method. The block unit value cut-off was either US$45 /t (bulk) or US$66 /t (selective).
  4. No allowances were made for mining losses or external dilution; planned internal dilution within the minimum stope size is included.
  5. In situ contained oxide reported.  Discrepancies in contained oxide values are due to rounding.

This Mineral Resource estimate is constrained by a base case price assumption of US$381 /kg Ta, representing a 20% increase over the Ta 2 O 5 metal price used to constrain previous Blue River Mineral Resource estimates.  The US$381 /kg base case price is approximately equal to the current price for Ta metal scrap and represents approximately a $100 /kg premium on tantalite concentrate. The higher price for Ta metal scrap compared to the price or Ta 2 O 5 in concentrate is considered to be a proxy to the added value Commerce could recognize by refining a Blue River concentrate into a high purity Ta 2 O 5 . Nb metal prices remain unchanged from 2010. The operating cost assumptions used to support the 2013 Mineral Resources reflect an average escalation of 12% over costs assumptions established for the project in 2010.

Table 2 shows the sensitivity of the Blue River Mineral Resources to tantalum metal price.  Sensitivities are based on a fluctuating metal price but could also represent fluctuating mining or processing costs or metallurgical recoveries or a combination of all of these factors.

Table 2: Blue River Project Sensitivity of Estimated Mineral Resources to Ta Price : Effective Date 21 June 2013 Tomasz Postolski, P.Eng.  Ta price was varied and all other assumptions remained the same.

                                                 
Ta price
[US$/kg]
      Confidence
Category
      Tonnes       Ta 2 O 5
[ppm]
      Nb 2 O 5
[ppm]
      Contained
Ta 2 O 5
[1000s of
kg]
      Contained
Nb 2 O 5
[1000s of kg]
564       Indicated       56,570,000       191       1,460       10,800       82,350
        Inferred       6,600,000       187       1,670       1,200       11,000
470       Indicated       54,400,000       193       1,490       10,500       81,250
        Inferred       6,200,000       189       1,690       1,200       10,500
381       Indicated       48,410,000       197       1,610       9,560       77,810
        Inferred       5,400,000       191       1,760       1,000       9,600
317       Indicated       41,189,000       201       1,760       8,280       72,670
        Inferred       4,600,000       194       1,870       900       8,500
272       Indicated       35,138,000       203       1,910       7,130       67,240
        Inferred       3,800,000       196       1,990       700       7,600
238       Indicated       29,916,000       204       2,030       6,110       60,740
        Inferred       2,800,000       198       2,060       600       5,800

Notes:  Base case is in bold.

Since underground mining methods are envisioned, the mining recovery may vary from 65% to 85% depending on the success in which pillars can be mined on retreat and/or fill is utilized.

Resource Classification and Methodology
The Mineral Resource is classified in accordance with the 2010 Canadian Institute of Mining, Metallurgy, and Petroleum (CIM) Definition Standards for Mineral Resources and Mineral Reserves, whose definitions are incorporated by reference into NI 43-101.

Geological interpretations were provided by Commerce to AMEC in the form of electronic three dimensional (3D) solid wireframes.  Capped drill core assays were composited down the hole to a fixed length of 2.5m respecting lithological boundaries.  Exploratory data analysis (EDA) was performed on the composites.  The coefficients of variation are low and support the use of linear grade interpolation methods such as inverse distance methods.  Blocks within the model were coded by lithology solids.  Specific gravity values were assigned by lithological unit.  Ta 2 O 5 and Nb 2 O 5 grades were estimated in the carbonatite using an inverse distance to the power of 3 (ID3) interpolation method.  A four-pass interpolation approach was used with each successive pass having greater search distances.  The block model grades were validated by visual inspection comparing composites to block grades on-screen, declustered global statistics checks, local biases checks using swath plots, and finally model selectivity checks.

The criteria are the same as those used in the June 22, 2012 , Mineral Resource. The current model also incorporates the most recent drill hole spacing studies completed by AMEC, and composites data statistics and variography which show little change from those used in the prior Mineral Resource. Resource classification is restricted to Indicated or Inferred, based on the following:

  • Confidence limits in drill hole spacing studies;
  • Concerns over analytical precision and provisional accuracy for the sample dataset from 2005 to 2008; and
  • Required metallurgical test work on the final stage of the proposed metallurgical process is still ongoing to support proof-of-concept.

To assess reasonable prospects for economic extraction AMEC assumed that the Upper Fir deposit would be mined utilizing self-supported, underground bulk mining methods under a conceptual scenario that considers mining and processing at a rate of 7,500 tonnes per day.

2011 PEA Outcomes and the Mineral Resource Update
Commerce completed a Preliminary Economic Assessment of the Blue River Project in 2011 (2011 PEA).  The findings of the 2011 PEA are summarized in an NI 43-101 compliant Technical Report prepared by AMEC and dated September 29, 2011.   The present 2013 Mineral Resource estimate includes greater tonnes but has similar grades compared with the Mineral Resource estimate used to support the 2011 PEA.

The 2011 PEA conceptual mine plan is based on a subset of the 2013 Mineral Resource estimate that remains essentially unchanged since 2011.  Capital and operating costs likely have increased since 2011 but AMEC is assuming that any increase in costs have been offset by the increase in the Ta price over the same period.  Overall AMEC concluded the 2011 Preliminary Economic Analysis (2011 PEA) outcomes remain reasonable and valid in 2013.

The PEA was prepared to define an overall proof of concept for further development of the Blue River Project. It indicated that the deposit can be developed economically as an underground mine and recommended future studies to support an eventual pre-feasibility level assessment of the project. The PEA included geological and mineral resource modeling, preliminary mine planning, a description of metallurgical test work and process design, a summary of environmental baseline work to date, and estimates for capital and operating costs. As well, it determined the economics to develop the project as an underground mine with process facility, and included an estimate of the direct cash costs to produce tantalum contained in a technical grade oxide product.  Readers are encouraged to review the entire PEA Technical Report which is available for viewing at www.sedar.com .  A link is also available on the Company web site at www.commerceresources.com .

In preparing the 2013 Mineral Resource update AMEC reviewed the 2011 PEA. AMEC considers that the following work and outcomes of the 2011 PEA remain reasonable as any cost escalation is considered to be offset by increases in long term Ta price:

  • Underground mining at 7,500 tpd using bulk mining with a variation of sublevel open stoping.
  • Total estimated capital cost to design and build is CAD$379M .
  • Operating costs over the life of mine are estimated at CAD$38.44 /t milled.
  • Cash costs of tantalum metal of CAD$24.91 /kg contained in a technical grade chloride product (after credit for the niobium contribution).
  • Production estimated at 2.7M t/a of mineral resources, over 9.3 years.
  • Estimated Internal rate of return:  9.1% (before tax). If the project is developed it will be subject to taxes which will result in cash flows and an NPV less than reported.
  • Estimated Net present value:  CAD$18.5 million at 8% discount rate (before tax).
  • Estimated Payback:  6.3 years.
  • Average diluted grade in the conceptual mine plan to the mill: 185 ppm Ta 2 O 5 and 1,591 ppm Nb 2 O 5.
  • Mineral processing using a standard grind-flotation procedure to produce a concentrate of ferrocolumbite-pyrochlore.
  • Metallurgical testing indicates that a mineral concentrate assaying about 30% combined Nb-Ta pentoxide with a Ta-Nb recovery of 65-70% is possible.
  • Proposed product:  High purity Ta and Nb chloride products containing 2,400 metric tonnes and 18,610 metric tonnes of the respective metals over the life of the mine and that are suitable for several markets.
  • Conceptual Mine Life :  9.3 years based upon the mineral resources (effective date 20 September 2011 ) defined for the PEA using information to the end of 2009 drilling.
  • NPV Sensitivity:  The Upper Fir deposit is most sensitive to changes in exchange rate, commodity prices, and mining costs.

Results of the Mineral Resource update and the PEA represent forward-looking information. The PEA is preliminary in nature and it includes Inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves, and there is no certainty that the PEA will be realized. Mineral resources are not mineral reserves as they do not have demonstrated economic viability.

Opportunities Arising from the Mineral Resource Update
Though a 25 Mt life-of-mine plan prepared in 2011 for the PEA remains valid, the 2013 Mineral Resource is larger than the 2011 Mineral Resource used to prepare the plan. This shows potential to extend the life-of-mine plan, though its impact on the economics of the Upper Fir deposit has not yet been examined. Further opportunities exist that may allow additional improvements to the economics of the project including optimizing the mine plan by mining higher grade zones earlier in the mine life and optimizing the mine layout to minimize development costs, as well as preparation of a geotechnical model to examine opportunities to increase the size of the stopes.

AMEC's Recommendations in Support of Prefeasibility Study
AMEC's recommended work program is expected to take two years to complete and will include the budgeted items recommended in Table 3 which follows.

Table 3: Summary of Proposed Work to Support a Pre-Feasibility Study (in CAD$)

Task Estimated
Budget
Comment
Database $50,000 Prepare standards for accuracy monitoring
Local Anisotropic Kriging:
mineral resource estimate
$40,000 Improve local grade estimate
Drilling $5,460,000 125 Infill, step-out, hydrological, and condemnation
holes, totaling 27,300m
Mineral Resource Update $400,000 Geologic interpretation and grade estimation
Mining studies $750,000 Geotechnical and hydrological models, mining
method, access, and ventilation
Metallurgical test work  $1,550,000 Flotation, filtration, and hardness test work. Preparation
of concentrate.  Aluminothermic and Chlorination test
work.
Co-disposal studies $400,000 Geotechnical/hydrological design
Environmental $400,000 Extend baseline studies to local infrastructure
Waste Rock Characterization $350,000 Static and kinetic geochemical testing
Marketing Studies $100,000 Examine marketing requirements
Project Management $2,400,000  
Sub-total $11,900,000  
Contingency $2,000,000 @ 20%
TOTAL $13,900,000 Pre-Feasibility Study

Comparison of Mineral Resources
The inclusion of the results from the 2011 drill campaign into the updated Upper Fir model has not resulted in any significant changes to the interpreted size or geometry, but has resulted in increased local confidence in the geometry and grade.

End Products and Base Case Metal Pricing
The processes proposed for the Upper Fir deposit will produce 99.9% pure tantalum and niobium oxides, generally known as technical grade oxide products. These products are generally sold under contract and the prices are typically kept confidential between buyer and seller to preserve competitive advantages. Tantalum and niobium price assumptions used to support the 2013 Mineral Resources are based on publically available and subscription service reports.

Tantalum
Tantalum is commonly quoted as two separate products:

  • Ta 2 O 5 in tantalite concentrate: a non-refined, tantalum-bearing concentrate of variable composition and trace element content; and
  • tantalum metal scrap (99.9% pure Ta): this form of tantalum product receives a premium price in the market relative to tantalite concentrate.

Between January 2010 and January 2013 , tantalite concentrate prices have risen from US$88 /kg to US$285 /kg. In the same period Ta metal scrap prices have risen from US$145 /kg to US$385 /kg. Prices rose dramatically in 2010 in response to changing market conditions including reduced production, increased concerns about tantalum mined from conflict regions (i.e. conflict tantalum), depletion of known strategic stockpiles, and curtailed exports from China . These market conditions remain in 2013.

Niobium
Nb generally trades as Nb metal, or ferroalloy, and the price has remained relatively constant at US$50 /kg Nb metal over the last several years.  A base case price of US$46 /kg Nb metal was assumed for consistency with previous estimates.

AMEC's Comment on Resource Update Price Assumptions
Tantalum is not a freely traded commodity and information regarding Ta and Nb market prices is not as readily available as it is for base and precious metals; Ta and Nb are typically sold on a contract basis. The Ta and Nb price assumptions used to support the Mineral Resource estimate and the preliminary economic analysis are based on current market trends which are considered volatile. AMEC concludes that the price assumptions used reflect current market conditions but acknowledges there is a risk these price assumptions may not reflect long term prices.

Comments of Commerce President
"We are again extremely pleased with the results of this study which represents a major milestone in the progress to develop the Upper Fir.  The  resource reported today is further confirmation of Commerce's belief that we are in the process of building a very important long-term source of conflict free and ethical tantalum which could potentially supply 10% of the current world's market for the long term." said Dave Hodge , Commerce's President. "Results of all the technical work completed to date give solid evidence of the quality of the mineral resource.  Commerce continues to be active in its search for a strategic partner who will work with us to define appropriate project financing options to support the recommended pre-feasibility studies."

Property
The Blue River Project is located near the village of Blue River , which is approximately 250 km north of the city of Kamloops and approximately 90km south of the town of Valemount . The Project comprises 105,373 hectares (1,000 km 2 ) of mineral claims. Power transmission lines, rail, and paved and gravel roads are all adjacent to, or within the property boundaries. Transalta Corp.'s 18 MW Bone Creek run-of-river hydroelectricity project near the project was commissioned in June 2011 .

NI 43-101 Disclosure
The following Qualified Persons for the report are AMEC employees, based out of Vancouver :  Mr. Greg Kulla , P.Geo., Principal Geologist,; Mr. Tomasz Postolski , P.Eng., Senior Geostatistician,;  Mr. Ramon Mendoza Reyes , P.Eng., Principal Mining Engineer,; Mr. Tony Lipiec , P.Eng., Director, Process Engineering, , and Mr. Behrang Omidvar , P.Eng; Financial Analyst.  All of the Qualified Persons have read and approved the contents of this news release that are extracted or summarized from the "Blue River Tantalum-Niobium Project, British Columbia, Canada , NI 43-101 Technical Report on Mineral Resource Update" with an effective date of June 21, 2012 .

Ms. Jenna Hardy , M.Sc., P.Geo., Commerce Resources Corp., is a Qualified Person as defined by National Instrument 43-101, read and approved the disclosure of the technical information in this news release with respect to the exploration.  A Technical Report compliant with National Instrument 43-101 standards summarizing the Mineral Resource Update will be filed on SEDAR ( www.sedar.com ) within 45 days.

About Commerce Resources Corp.
Commerce Resources Corp. is an exploration and development company with a particular focus on tantalum, niobium and rare metal deposits with potential for economic grades and large tonnages. The Company is specifically focused on the development of its Upper Fir Tantalum and Niobium Deposit in British Columbia and its Ashram Rare Earth Element Project in Quebec .

On Behalf of the Board of Directors
COMMERCE RESOURCES CORP.

"David Hodge"
David Hodge
President and Director
Tel:  604.484.2700
Email: dhodge@commerceresources.com

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Forward-Looking Statements
This news release contains forward-looking information which is subject to a variety of risks and uncertainties and other factors that could cause actual events or results to differ from those projected in the forward-looking statements.  Forward looking statements in this press release include that we will have positive cash flow for a potential 7,500 tonnes per day underground operation at the Upper Fir property with cash costs of CAD$24.91 per kilogram of tantalum metal; that we will have opportunities for optimization in the geology and mining areas and enhance the quality of the resource; that prices for our potential products are conservatively estimated and may trend upwards; that our property has Indicated Mineral Resources totalling 48.4 million tonnes at 197 ppm Ta 2 O 5 and 1,610 ppm Nb 2 O 5 .  Inferred Mineral Resources total 5.4 million tonnes at 191 ppm Ta 2 O 5 and 1,760 ppm Nb 2 O 5; that total estimated capital cost to design and build a mine is CAD$379M and other assumptions listed will be accurate;  that operating costs over the life of mine are estimated at CAD$38.44 /t milled; and the projected method of mining and its results will be accurate.  These forward-looking statements are based on the opinions and estimates of management and its consultants at the date the information is disseminated.  They are subject to a variety of risks and uncertainties and other factors that could cause actual events or results to differ materially from those projected in the forward-looking information .   Risks that could change or prevent these statements from coming to fruition include changing costs for mining and processing and their impact on the cut off value established; increased capital costs;  changing forecasts of mine production rates; the timing and content of upcoming work programs; geological interpretations based on drilling that may change with more detailed information; potential process methods and mineral recoveries assumption based on limited test work and by comparison to what are considered analogous deposits that with further test work may not be comparable; the availability of labour, equipment and markets for the products produced; market pricing for the products produced; and despite the current expected viability of the project, conditions changing such that the minerals on our property cannot be economically mined, or that the required permits to build and operate the envisaged mine can be obtained. The forward-looking information contained herein is given as of the date hereof and the Company assumes no responsibility to update or revise such information to reflect new events or circumstances, except as required by law.

For a description of the data verification procedures, analytical and testing procedures and a description of the identification of any known legal, political, environmental, or other risks that could materially affect the potential development of the mineral resources, see "Blue River Ta-Nb Project NI 43-101 Technical Report on Mineral Resource Update", by AMEC with effective date 21 June-2013 that is filed on SEDAR. 

SOURCE Commerce Resources Corp.

Scroll down for more posts ▼

Top 10 Most Recent News Articles

A $26.95 Ornament With a Serious 250th-Year Mission

Updated Category News Views 61

Brass, linen, and a 24-karat gold finish are doing more work here than holiday sparkle. The White House Historical Association's 2026 official Christmas ornament is built around America's 250th anniversary, using a modest $26.95 collectible to make the founding story physical, visible, and—ideally—worth keeping after the tree comes down. A Small Product Carrying a...

Continue Reading
Alphabet's AI Spending Shock Meets a New Shareholder Lawsuit

Updated Category News Views 81

Alphabet’s AI story hit a pothole big enough to rattle every growth investor holding the wheel. A proposed securities class action, Stewart v. Alphabet Inc. et al., targets buyers of Alphabet securities between May 19, 2026, and October 28, 2026. The allegation is not merely that a product timetable slipped. It is that investors were given a rosier picture of Gemini 3.5...

Continue Reading
Nord Anglia Tests 20 Minutes of Early Independence

Updated Category News Views 13

Twenty minutes of purposeful classroom freedom is a modest wager, yet Nord Anglia Education's latest findings make it worth watching. The international schools group says its daily “Flag Time” routine helped children aged three to six become more self-directed: better at planning, persisting, making choices and judging their own progress. In an education market...

Continue Reading
Columbia Sunroom Costs Start With the Unseen Work First

Updated Category News Views 73

A bright room can turn into a dark money pit before the first window arrives. That is the plain lesson in Steven McCoy’s discussion of sunroom pricing for Columbia, South Carolina homeowners. People see glass, a roofline and some extra square footage; contractors see excavation, structure, insulation, electrical work, mechanical systems, permits and a whole pile of...

Continue Reading
Amdocs Faces Inquiry After T-Mobile Fallout Hits Shares

Updated Category News Views 50

A telecom software contract turned into a trapdoor for Amdocs shareholders this month. On November 4, shares of NASDAQ:DOX fell roughly 30%, one day after the company disclosed a dispute involving its recently signed T-Mobile agreement. That kind of move is not a routine earnings wobble. It is the market abruptly repricing a business relationship investors had been told...

Continue Reading
Drew Schaffer's Award Highlights Veterans Legal Aid

Updated Category News Views 90

Some recognition notices are corporate wallpaper; this one has actual weight. Greenberg Traurig associate J. Andrew “Drew” Schaffer received the Pro Bono Associate of the Year Award at Orange County’s 30th Annual Justice Sheila Sonenshine Pro Bono Reception, and the reason matters more than the plaque. His work has centered on veterans trying to navigate discharge...

Continue Reading
Ajman's First Media Forum Puts Trust Before AI Hype

Updated Category News Views 58

A Question With Real Consequences Deepfakes have made the old newsroom race for speed look downright quaint. Ajman's first Media Forum, called The Signal, put a far more useful question on the table: who owns the signal when machines can produce a convincing imitation of nearly anything? Held on November 18 and 19, 2026, the event gathered 68 speakers from 17 countries,...

Continue Reading
Vista Social Data Puts Question Hooks on Notice Today

Updated Category News Views 15

Marketing folklore just took a fairly deserved punch in the nose. Vista Social examined 1.2 million posts from more than 22,000 brand profiles and found that opening a video with a question lowered engagement on every one of the seven networks it measured. A bold statement did better across the board. That is not some sexy, mystical creative revelation. It is a useful...

Continue Reading
Curve Voice Tests the Value of a Native Front Desk

Updated Category News Views 21

A ringing dental-office phone is a tiny operational mess with surprisingly expensive consequences. Curve Dental is aiming straight at that mess with Curve Voice, an upcoming native phone system built inside its cloud-based practice-management platform. The company says commercial availability for existing Curve Dental customers is expected in February 2027, following a...

Continue Reading
Uniform Advantage Fills a Retail Void Across 11 States

Updated Category News Views 144

A Useful Bet on an Unfashionable Retail Need Sixteen former Scrubs & Beyond storefronts have landed with Uniform Advantage, and this is one of those retail moves that looks a lot more sensible than flashy. Healthcare workers do not buy scrubs like they buy a novelty T-shirt online at midnight. Fit, fabric, pockets, color requirements, and comfort over a punishing shift...

Continue Reading

Top 5 Most Recently Viewed Articles

DefectDojo Secures $7 Million to Boost AppSec Capabilities

Updated Category News Views 89

DefectDojo Secures $7 Million to Improve Application Security DefectDojo, a prominent player in the field of scalable application security, has recently made headlines by raising $7 million in funding. This investment will help speed up the development of its innovative solutions aimed at enhancing application security. The funding round, mainly supported by Iolar...

Continue Reading
Investigation into MoonLake Immunotherapeutics' Recent Losses

Updated Category News Views 305

Investigation into MoonLake Immunotherapeutics' Recent Losses Faruqi & Faruqi, LLP, a prominent national securities law firm, has initiated an investigation concerning potential claims on behalf of investors of MoonLake Immunotherapeutics (NASDAQ: MLTX). This development comes after the company's stock experienced a significant downturn, raising concerns among...

Continue Reading
Biohaven's Director Bailey Gregory Invests $221K in Shares

Updated Category News Views 205

Bailey Gregory Makes a Major Investment in Biohaven Recently, Bailey Gregory, a prominent director at Biohaven Ltd. (NYSE:BHVN), made a splash by acquiring 5,000 shares of the company's stock for about $221,000, averaging $44.19 per share. This purchase not only reflects Gregory's confidence in Biohaven but also highlights a strong commitment to the company's future...

Continue Reading
Messer Invests Significantly in New Air Separation Unit

Updated Category News Views 484

Messer Expands Presence with New Air Separation Unit Messer, a prominent industrial gases provider, is undertaking a substantial investment exceeding $70 million to establish a state-of-the-art air separation unit (ASU). This initiative is designed to cater to the growing demand for industrial gases, a crucial resource for numerous sectors. A Commitment to Growth...

Continue Reading
Transforming Crypto Mining: The Role of USDC and DRML Miner

Updated Category News Views 347

Revolutionizing Cloud Mining with DRML Miner and USDC The cryptocurrency landscape is evolving rapidly, with many companies striving to make their mark. Among them is DRML Miner, a pioneer in the mining industry, dedicated to merging innovation, sustainability, and user accessibility. The company has consistently pushed boundaries by harnessing green energy and advanced...

Continue Reading