Avalon Announces Results of Positive Feasibility Study for

New Post Public Reply Private Reply Replies (0) Message Board
News Desk 2018
Avalon Announces Results of Positive Feasibility Study for the Nechalacho Rare Earth Elements Project

TORONTO, ONTARIO--(Marketwired - April 17, 2013) - Avalon Rare Metals Inc . ( TSX :AVL)(NYSE Amex:AVL)( NYSE MKT :AVL) ("Avalon" or the "Company") is pleased to announce the completion of a positive Feasibility Study ("FS") for its Nechalacho Rare Earth Elements Project (the "Project"). The FS was prepared by SNC-Lavalin Inc. ("SLI") and is the first feasibility level study to be completed on a major heavy rare earth project outside of China. The FS results confirm that the Project is technically feasible and economically robust.

Feasibility Study Highlights

  • The discounted cash flow ("DCF") analysis yields a 22.5% internal rate of return ("IRR") on a pre-tax basis and a 19.6% IRR on an after-tax basis, assuming 100% equity financing. The Project's net present value ("NPV") at a 10% discount rate is $1.351 billion (1) pre-tax and $900 million after-tax.
  • Total Project construction capital costs are $1.575 billion, which is inclusive of a 13% contingency and $122 million in sustaining capital. Of the total capital costs, approximately $1.152 billion is expected to be incurred in the Northwest Territories and $423 million is expected to be incurred in Louisiana.
  • Operating costs average $264.5 million per year
  • Revenues average $645.8 million per year ($456.5 million from separated rare earth oxides ("REO") and $189.3 million from the sale of an enriched zirconium concentrate ("EZC")).
  • Revenues from HREE (2) are in excess of 50% of total Project revenue.
  • Sales of the five critical REO (neodymium, europium, terbium, dysprosium and yttrium) account for over 82% of the separated REO revenues.
  • Lanthanum and cerium sales represent less than 4.5% of total revenues.
  • Total Measured and Indicated Mineral Resources would conceivably be sufficient to support continued mining operations at Nechalacho for over 90 years, if the mining rate is unchanged and Mineral Resources are converted to Mineral Reserves at the same conversion rate experienced in the FS.

Don Bubar, President and CEO stated, "We are very pleased to have delivered a positive Feasibility Study for the Nechalacho Project within the budget and the schedule we set for ourselves in May, 2012. The robust economics, despite a substantial CAPEX burden, testify to the exceptional quality of the Nechalacho deposit and its large size offers the potential for creating a scalable, multi-generational business. The successful completion of this study confirms Nechalacho's status as the most advanced major heavy rare earth element project in the world outside China. With the FS in hand, we can now accelerate the process of securing commitments on future product sales and attracting financial partners to participate in the further development of the Project."

Feasibility Study - Key Metrics

The Project financial model assumes 100% equity financing although the Company anticipates that the Project will be financed through a combination of debt and equity. The release of this FS is a critical step toward securing the project financing needed to support the construction of the Project through to steady state operation.

Metric Quantity Units
Economics (Pre-Tax)
IRR 22.5 %
NPV @ 8% 1,833 $million
NPV @ 10% 1,351 $million
NPV @ 12% 981 $million
Economics (After-Tax (3) )
IRR 19.6 %
NPV @ 8% 1,262 $million
NPV @ 10% 900 $million
NPV @ 12% 620 $million
Payback Period 4.3 years
Mining
Mineral reserves 14,600,000 tonnes
Production rate 730,000 tonnes per year
Initial Mine Life 20 years
Total Revenue 645.8 $million per year
Rare earth oxides 456.5 $million per year
EZC 189.3 $million per year
Unit basis 884.65 $ per tonne mined
Total Operating Costs 264.5 $million per year
Reagents 97.2 $million per year
Fuel and Power 50.7 $million per year
Labour 36.7 $million per year
Freight 29.4 $million per year
General and Administration 26.8 $million per year
Other 23.7 $million per year
Unit basis 362.28 $ per tonne mined

Sensitivity analyses on the Project financial model demonstrate that pre-tax Project NPV at a 10% discount rate is most sensitive to metallurgical recoveries, TREO pricing, Canada/US exchange rate, and production tonnage.

The expected annual average production of separated REE (4) in oxides and REE carbonate products (quoted as oxide equivalents) over the 20 year initial mine life are set out in the table below.

Annual Production Averages (in tonnes per year), over 20 year mine life
Oxide (5) Contained in EZC Separated Rare Earth Oxides Total
La 2 O 3 193.2 1,187.6 1,380.8
Ce 2 O 3 502.6 2,521.6 3,024.2
Pr 2 O 3 58.8 322.3 381.1
Nd 2 O 3 349.0 1,179.9 1,528.9
Sm 2 O 3 122.2 220.9 343.1
Eu 2 O 3 16.1 31.5 47.6
Gd 2 O 3 121.2 231.5 352.7
Tb 4 O 7 21.0 37.6 58.6
Dy 2 O 3 128.6 195.8 324.4
Ho 2 O 3 27.9 32.5 60.4
Er 2 O 3 89.2 71.6 160.8
Tm 2 O 3 13.8 8.0 21.8
Yb 2 O 3 89.9 40.0 129.9
Lu 2 O 3 13.5 4.6 18.1
Y 2 O 3 728.8 724.9 1,453.7
2,475.8 6,810.3 9,286.1
ZrO 2 19,763.3 - 19,763.3
Nb 2 O 5 2,230.5 - 2,230.5
Ta 2 O 5 243.0 - 243.0
Total 24,712.6 6,810.3 31,522.9

The table below sets out the anticipated capital expenditures for the Project, broken down by the jurisdiction to which each class of expenditure relates.

Cost Category NWT LA Total
Mine Development 81.58 - 81.58
Main Process Facilities 351.24 192.51 543.75
Infrastructure 150.68 78.82 229.50
EPCM 119.27 38.57 157.84
Indirect Construction Costs 175.56 27.25 202.81
Owner's Costs 36.76 18.95 55.71
Contingency 120.91 44.90 165.81
Closing Costs / Bond 13.00 3.16 16.16
Upfront Capex 1,049.00 404.16 1,453.16
Sustaining Capital 102.72 19.12 121.84
Total Capex 1,151.72 423.28 1,575.00

The CDN:USD exchange rate assumption used in the FS for the economic evaluation was based on a major bank's forecast prepared during January, 2013 as follows:

Year CDN:USD
To end of 2015 Cdn$1.00 = US$0.97
2016 Cdn$1.00 = US$0.96
2017 and thereafter Cdn$1.00 = US$0.95

For reference, the foreign exchange rate assumption used in the Company's prefeasibility study ("PFS"), the results of which were disclosed in the Company's news release dated July 7, 2011 , was Cdn$1.00 = US$0.95.

The FS is the culmination of extensive resource definition, engineering, environmental and metallurgical studies carried out over the past two years at a total cost of approximately $60 million, as outlined in the table below:

Category ($ Million)
Resource Definition 23.0
Metallurgy 17.0
Feasibility Studies 15.0
Environmental and Permitting 3.0
Community Engagement 2.0
Total 60.0

The FS covers all aspects of project development, including mining, mineral concentration, hydrometallurgical processing, refining and separation of individual rare earth oxides as well as all related infrastructure. SLI developed its capital and operating cost estimates from first principle capital quotations, estimates from suppliers, manufacturers, contractors and experience based on comparable operations in Canada and abroad. The capital and operating cost estimates were completed to a level consistent with an AACEI Class 3 estimate, with an intended level of accuracy of ±15%, based on Q2 2012 prices, excluding escalation.

Optimization Opportunities and Next Steps

While the economics contained in the FS are robust, ongoing metallurgical process development work and engagement with consumers in the marketplace has allowed the Company to identify several major and numerous minor Project optimization opportunities. These could significantly improve the Project economics with lower Capex and Opex, reduced technical risk, enhanced metallurgical recoveries, and other operational efficiency improvements.

These optimization opportunities include (but are not limited to):

  • optimization of the crushing and grinding circuit, plant layouts and materials of construction;
  • metallurgical testwork to further improve reagent selection and flotation recoveries;
  • improvements to the Hydrometallurgical Plant processes;
  • alternative impurity removal scenarios;
  • potential to separate lanthanum and cerium at the Hydrometallurgical Plant and stockpile for future sales;
  • potential to reintroduce cracking of zircon at a later date to increase direct production of HREE and separate the by-products from the EZC;
  • potential sales of a magnetite by-product;
  • potential to defer the construction of the Refinery and toll process Avalon's mixed rare earth concentrate through a refinery (or refineries) built and operated by others; and
  • potential to use excess capacity in the Refinery to toll process third party production and reduce operating costs.

The Company is already investigating most of these opportunities and will continue to refine the Project development model as potential benefits are tested and confirmed.

In the meantime, critical path work including preliminary engineering for the Nechalacho Mine and Concentrator infrastructure is underway, as are preparations to engage a contract miner for the underground development work. The precise timing for the initiation of underground development work planned for 2013 has yet to be finalized. However, this work is unlikely to begin this summer as originally contemplated due mainly to uncertainty on the timing for receipt of requisite land use permits.

Further, the current state of equity markets for the resource industry in general, as well as the rare earth industry, may limit the Company's short term financing opportunities. However, this will permit the Company to focus on Project optimization over the next four to six months, which will limit the erosion of its treasury from large Project development expenditures. The Company believes that this should not impact the Project completion schedule and the Company still anticipates being able to bring product to market in 2017.

The key factors going forward influencing the timely execution of the Project are: securing a strategic or financial partner, timely receipt of all requisite operating permits and approvals, securing sufficient binding agreements for offtake to support project financing, and the availability of equity and debt financing at a reasonable cost.

Review of the FS Project Development Model

The Project will consist of facilities located at three separate sites: an underground mine and concentrator to be located at Thor Lake, 100 kilometres southeast of Yellowknife, Northwest Territories ("NWT") (the "Nechalacho Mine and Concentrator"), a hydrometallurgical plant to be located at Pine Point, 85 kilometres east of Hay River, NWT (the "Hydrometallurgical Plant"), and a rare earth refinery to be located in Geismar, Louisiana ("LA") (the "Refinery"), which will produce high purity separated REE oxides and carbonates.

The development model in the FS incorporates two fundamental changes to the original model used for the PFS: the inclusion of the Refinery (whereas the PFS contemplated selling a mixed REE concentrate at a discount to market prices for separated REE oxides) and the exclusion of the zircon "cracking" process.

The decision to include the Refinery in the FS development model was made after several potential consumers expressed a desire to see a refining solution outside of China. At the present time, there are no rare earth refineries outside of China with the capability of processing HREE in the quantities that the Project is expected to produce, and there is no guarantee that such a refinery will be built by others. In addition, many consumers are insisting that suppliers provide assurances that their rare earth products have been produced in a socially and environmentally responsible way. Building the Refinery into the FS development model better positions Avalon to provide such assurances and meet its corporate commitment to sustainability.

Secondly, the PFS contemplated "cracking" the zircon contained in the leached solids from the Hydrometallurgical Plant to recover zirconium, niobium, tantalum and further LREE (6) , and HREE, while the FS provides for the direct sale of the material to processors in Asia as EZC. In so doing, potential technical risks associated with the cracking process were eliminated and a reduction in the related capital costs was achieved, while retaining the optionality of building zircon cracking into the business at some future date.

The development model in the FS provides for construction of the Nechalacho Mine and Concentrator site to begin first (basic engineering work on the flotation section has already commenced). This will be followed by the Hydrometallurgical Plant and the Refinery. Construction work at each site is scheduled such that each facility is available to receive feed as soon as production becomes available from the supplying facility. In addition, provision is made to start commissioning the Hydrometallurgical Plant using high grade ore shipped directly from the mine ahead of concentrate being produced by the Nechalacho Concentrator. This will shorten the overall ramp-up period and reduce the schedule risk from any delay in commissioning of the concentrator.

Nechalacho Mine and Concentrator

The heavy rare earth rich Basal Zone ore body is a sub-horizontal, gently undulating layer, situated at an average depth of approximately 200m, that varies from 5m to over 30m in thickness (averaging 20m across the whole deposit). The FS provides for the construction of a 2,000 tonne per day ("tpd") underground mine and concentrator. This facility is expected to ramp up to its design capacity of 730,000 tonnes a year within six months after commencement of mining. The mine will be developed as a cut and fill operation with lower-cost long hole stoping methods used in the thicker parts of the ore body. Mine access will be by ramp, with primary crushing underground. Crushed material will be delivered to surface by conveyor. Mining will be conducted with a first pass of primary stopes, followed by secondary stope extraction after the primary stopes have been cement paste-backfilled.

Mined ore will undergo a crushing operation to reduce rock size to 80% passing 13.5mm. The crushing facility has been designed to treat over 4,000 tpd to accommodate the potential doubling of the initial planned mining rate at a future date. Crushed ore from underground will be brought to surface by conveyor, fed into a rod/ball mill circuit and de-slimed ahead of flotation. A magnetite product can also be produced from this milling operation, and Avalon is assessing sales opportunities for this product.

The flotation section of the Concentrator is comprised of rougher and multiple cleaner circuits to produce a flotation concentrate which is further up-graded by gravity concentration to produce a final concentrate typically consisting of over 7.37%TREO, 15.53% ZrO 2 , 1.71% Nb 2 O 5 , and 0.19% Ta 2 O 5 . This final concentrate is filtered and stored in a covered bulk facility on site from which it will be loaded into concentrate shipping containers, hauled to the seasonal dock facility on the north shore of Great Slave Lake and barged during the summer to the Hydrometallurgical Plant.

The Nechalacho Mine and Concentrator infrastructure will include an environmentally responsible tailings management facility located in a local catchment area to the northeast of Thor Lake, a 120 person camp, 1,000 metre airstrip, diesel power generation for a peak demand of 13.6 megawatts ("MW") at 2,000 tpd, administration, maintenance and warehouse facilities and a seasonal dock facility for concentrate loading.

Hydrometallurgical Plant

Scroll down for more posts ▼

Top 10 Most Recent News Articles

AppLovin Legal Woes: A Deep Dive into Investor Claims

Updated Category News Views 250

AppLovin Faces Legal Heat and Market Scrutiny Bitter truth has a way of crashing like a wave, and AppLovin (NASDAQ: APP) is feeling the brunt of it. Now knee-deep in a securities class action, the firm’s been accused of selling fairy tales about its AI capabilities, leaving investors clutching at substantial losses. If you’ve been banking on their promises between...

Continue Reading
EFICYENT Ventures to Connect at Singapore FinTech Fest

Updated Category News Views 226

Why the Singapore FinTech Festival Matters The world's hardly a stranger to hype, but the Singapore FinTech Festival carries some real weight. From November 18 to 20, 2026, this gig isn't just industry chatter—it's a high-stakes convergence of policymakers, financial institutions, fintech innovators like EFICYENT, and the money folk looking to mold the future of...

Continue Reading
Retirement Dreams Dashed: 61% Withdraw Early

Updated Category News Views 342

Retirement Caught in the Crosshairs Just when you think the path to retirement might clear up, life slaps down older workers with economic reality. A recent LiveCareer survey underscores this financial mess, revealing that 61% of those 50 and older are raiding their own retirement funds to make ends meet. It's enough to make one's head spin. Inflation: The Unwanted Guest...

Continue Reading
Webull Faces Class Action: Key Details for Investors

Updated Category News Views 254

What's Really Going on With Webull? When you hear there's a class-action lawsuit brewing, you know something's gone real sideways. Webull Corporation (NASDAQ: BULL) finds itself neck-deep in a securities fraud class action alleging some dicey dealings with China. If you've got skin in the game—and if you bought Webull stock between April 26, 2025, and October 6,...

Continue Reading
Shenzhen's Vision Unveiled: APEC 2026 Promo Debut

Updated Category News Views 148

Shenzhen's Spotlight Moment at APEC 2026 When Shenzhen announced its promotional video for the 2026 APEC Economic Leaders' Meeting, it wasn't just about standard tourism glitz. This was a show of force, a bold step onto the main stage of global politics and economics. The video's launch wasn’t merely an audio-visual delight—it staked a claim in shaping the future...

Continue Reading
WeaveGrid Powers EVConnectNC: Charging Incentives Launched

Updated Category News Views 213

Transforming Utilities with EVConnectNC In a fresh move by WeaveGrid, North Carolina's Electric Cooperatives have teamed up to roll out EVConnectNC. This innovative program aims to manage the burgeoning demand for electric vehicle (EV) charging in rural and suburban areas under North Carolina's cooperative umbrella. Think of it as a smart way to handle new loads without...

Continue Reading
YSTUDIO's Pens: A Nod to the Power of Writing

Updated Category News Views 445

Slow Down, Write On: A New Era for Stationery In a world where sentiments zip around with a swipe, here we find YSTUDIO tapping into something analog and profound. Their latest offerings—a 'Brand Day Gift Box' and the 'Inner Universe' pen series—are more than just high-end stationery. They’re an invitation to reconnect with the written word, a gesture to slow our...

Continue Reading
El Pollo Loco Faces Class Action Over Wage Practices

Updated Category News Views 407

Alright, here's where things start sizzling—El Pollo Loco, the fast-food chicken chain whose name translates to 'The Crazy Chicken'—is in a legal pickle. The lawsuit hanging over their heads could spell a sticky situation for them and possibly ripple through the fast-food industry. The suit, filed by the steadfast firm Blumenthal Nordrehaug Bhowmik De Blouw LLP, has...

Continue Reading
PASCAL's Holiday Gift Edit: Timeless Watches Shine

Updated Category News Views 363

Fresh Sparkle for the Holidays Well, here we are again, staring down the barrel of another holiday season. And what do you know, PASCAL is out with its 2026 Holiday Gift Edit, like clockwork. This is the kind of stuff they’re good at—capturing a moment, slapping some color on it, and calling it a game-changer. Launching on November 14, this edit nods to their Timeless...

Continue Reading
Advanta's Game-Changer: Acquiring Misr Hytech to Expand in Africa

Updated Category News Views 364

Advanta's Strategic Move into Africa Alright, let's cut to the chase. Advanta is making a big splash with its acquisition of Misr Hytech, a move that's going to shake things up in Africa's agricultural sector. This isn't just another merger to gloss over with your morning coffee. We're talking about a deal that's supposed to wrap up by January 31, 2027, bringing together...

Continue Reading

Top 5 Most Recently Viewed Articles

Robbins LLP Invites New Fortress Energy Shareholders to Connect

Updated Category News Views 275

New Fortress Energy Inc. faced a class action lawsuit back in 2024, hitting hard on shareholders who bought into their promises but got burned instead. Robbins LLP threw down the gauntlet, encouraging those left holding the bag after misleading reports to seek compensation for their losses. Investor Fallout: What’s at Stake with NFE? This suit isn’t just some legal...

Continue Reading
Sasol Limited Board Welcomes New Leadership and Committees

Updated Category News Views 289

Sasol Limited Board Welcomes New Leadership and Committees Sasol Limited is ushering in a new era with the appointment of Ms. Muriel Dube as the new Chairman of the Board. Her robust experience in sustainability and leadership will be pivotal as she takes on this important role, bringing a vision that emphasizes both sustainability and innovation. Introducing the New...

Continue Reading
Nutriband Welcomes Back Gareth Sheridan as CEO for New Goals

Updated Category News Views 229

Nutriband's Leadership Transition and Future Goals Nutriband Inc. has announced the return of its founder, Gareth Sheridan, as CEO, following a brief period where co-founder and Chairman, Serguei Melnik, assumed leadership duties. Sheridan's reappointment is seen as a strategic move to guide the company through its pivotal developments, especially as the firm approaches...

Continue Reading
Explore Top Mobile Gaming Apps for Programmatic Success

Updated Category News Views 247

Recognizing the Best Mobile Gaming Apps In the fast-paced world of mobile gaming, understanding the quality of programmatic advertising traffic is crucial for success. This March, a report unveiled compelling insights into the top mobile games available on the Apple App Store and Google Play Store. This ranking, grounded in evidenced performance metrics, offers a detailed...

Continue Reading
transcosmos Boosts Children's Education in Vietnam

Updated Category News Views 19

transcosmos Shifts from Green Initiatives to Education These days, the winds of change are catching companies looking to embed themselves deeply in social responsibility pursuits, and transcosmos stands out with its focus on Vietnam. This year, they're flexing a muscle in education. Gone are the days where tree planting alone was the highlight—although, don't get me...

Continue Reading