Solar is the wave of the future for clean, renewab
Post# of 10339
![](/assets/46931549/no_avatar_available_thumb.jpg)
From the company's official Twitter account:
Sun Pacific Holding Corp@SunPacificPower
1GW Solar manufacturing plant for an existing building as per suppliers $SNPW
- Equipment Delivery: 100 days after down payment received
- Shipment & customs clearance to project site: 50 days (expected)
- Installation: 30-45 days
- Commissioning: 45-60 days
- Ramp up: 30 days.