3/19/19 Initial construction has begun with the
Post# of 22454
Quote:
3/19/19
Initial construction has begun with the foundation test pilings now being completed and non-destructive testing now underway. [3/19/19 PR]
Quote:
06/13/19
The required battery of soil, pile load and water quality tests have all been completed at this time. Finish grading and secondary ground preparations for the project area have also been completed and facilities construction work will be commencing at this time." [06/13/19 PR]
Quote:
7/23/19
Test piling for the quantum dot facility has been completed and the structural design is being finalized at this time.
As soon as the monsoon season is finished, we will be starting on piling and substructure work followed by superstructure works and we are confident that all above-ground construction of the building will be completed by November/December 2019.
At this time we are negotiating with local building contractors/subcontractors and expect to commence above ground construction in early August of this year.” [7/23/19 PR]