Looks like CinarSan is not the major builder,as announced late last year. I wondered if they were big enough to run two projects at the time shala and Kalavic,my opinion.
Article
The Ministry of Infrastructure and Energy announced that it has concluded the negotiation and signed the contract with the winning subject of the competition for the construction, operation and transfer with concession of the Kalivaç hydropower plant.
The Ministry of Infrastructure and Energy announced that it has concluded the negotiation and signed the contract with the winning subject of the competition for the construction, operation and transfer with concession of the Kalivaç hydropower plant.
The announcement of the winning company in this competition was carried out at the end of October 2017 and during the following months the negotiation of the terms of the contract and its signing was completed.
The Ministry of Infrastructure and Energy says that the winning consortium "Temporary Enterprise Union" Ayen Enerji "and" Fusha "shpk is foreseen to carry out an investment in the total value of 125,287,800 Euros.
The company 'Fusha' shpk is specialized in the construction field where one of the most recent Skanderbeg Square construction. While the other company 'Ayen Enerji' based in Turkey is specialized in the energy sector with investments in this sector both in Slovenia and Serbia.
The installed power determined by the calculator is 111,000 KW, the annual electricity output is over 366 million KWH and the time of implementation of the works for the work is 30 months.
According to the Ministry of Infrastructure and Energy, the successful completion of the procedure paves the way for the concreteization of one of the most important hydropower works in the country, suspended for many years.
TV report has learned that the deadline for the construction of this hydropower plant is 30 months. The history of Kalivaç's hydroelectric power plant started in 1997 when the project was initially signed by Fatos Nano, was strongly opposed by Berisha in opposition, but was approved by Berisha himself when he came to power. The project at first glance was great, the largest of the time - 350 GW of clean energy per year, within 5 years.
According to the 1997 contract signed by the Albanian government with businessman Francesco Beketi, energy production was expected to start in 2002, which never happened. Some earlier the Albanian government won another trial with Blach in arbitration for not respecting the contract by the latter.