Catalyst 4 This should be completed within the ne
Post# of 39368
Catalyst 4
This should be completed within the next 14 days. We will hear something early next year. I figure mid Jan. soonest.
San Juan 3 and 4:
We have applied for 2 additional Permits for wells a mile north of the initial San Juan Wells. We are currently acquiring casing, pipes, and mud to be loaded during the next 2-3 days out of Houston. The truck is expected to leave Houston by Thursday and to arrive in Belize on Monday morning. We will be clearing the location and preparing the pad sites by this weekend and expect to begin drilling sometime around the week of December 26th. We expect drilling to take around 5-7 days.
Max Mohamed
Project Manager