McEwen Mining Provides First Quarter 2012 Operational and DevelopmentUpdate

May 8, 2012 16:31:17 (ET)

TORONTO, ONTARIO, May 08, 2012 (MARKETWIRE via COMTEX) -- McEwen Mining Inc. ( MUX , Trade ) is pleased to provide a summary of the First Quarter, including operational and development updates for its projects in Argentina, Mexico and Nevada.

Balance Sheet $66.7 Million Liquid Assets - No Debt

At the end of the First Quarter, McEwen Mining had cash and liquid assets of US$66.7 million, comprised of cash of US$41.1 million, silver and gold bullion at market value of US$21.4 million, short-term investments of US$3.1 million and marketable securities of US$1.1 million. The company continues to hold a significant portion of its treasury in bullion with the belief that prices will continue to rise. The company remains debt free.

On February 24, 2012, McEwen Mining received its first dividend payment from its 49% ownership in the San Jose mine, totaling US$9.4 million. We expect to receive further dividends from the San Jose mine during 2012, although the timing and amount will depend upon precious metals prices, production levels, operating costs, capital expenditures, Argentine central bank and government restrictions, other factors beyond our control.

For the remainder of 2012, company-wide exploration and construction expenditures, including down payments on long lead time equipment for El Gallo Phase 2, are expected to total approximately US$50 million. This amount will be funded with existing cash and liquid asset balances, expected dividends from the San Jose mine and cash flow from Phase 1 of the El Gallo Complex, which is expected to commence production during the second half of the year.

San Jose Mine, Argentina (49%)

Final production results for the San Jose mine during the First Quarter totaled 20,357 ounces of gold and 1,355,678 ounces of silver or 45,936 ounces of gold equivalent (converting the silver into gold using a 53:1 exchange ratio) (100% basis). The San Jose mine remains on target to meet full-year production guidance of 85,000 ounces of gold and 5.7 million ounces of silver or 192,500 ounces of gold equivalent.

Cash Costs during the period totaled US$697 per ounce gold and US$13.90 per ounce silver on a co-product basis (calculated by applying the attributable cost to each ounce of gold and silver produced). Gold equivalent cash costs totaled US$719 per ounce gold (converting the cash cost of producing an ounce of silver into the gold equivalent using a 53:1 exchange ratio). The average grade of ore processed during the First Quarter was 5.98 gpt gold and 416 gpt silver. Gold and silver recoveries averaged 91.6% and 87.8%, respectively.

During the First Quarter 15,250 meters of diamond drilling was completed at the San Jose mine. This year a total of 110,000 meters or $14 million has been budgeted for exploration at the mine. This represents more than double the 2011 exploration budget.

 -----------------------------------------------------------------------
-----
-----------------------------------------------------------------
-----------
SAN JOSE MINE PRODUCTION                          Q1          Q4          Q1
COMPARISION (100% BASIS)(i)                     2012        2011        2011
----------------------------------------------------------------------------
Ore production (tonnes)                      115,531     126,675     113,696
----------------------------------------------------------------------------
Average head silver (gpt)                        416         412         459
----------------------------------------------------------------------------
Average grade gold (gpt)                        5.98        5.68        6.08
----------------------------------------------------------------------------
Average silver recovery (%)                     87.8        86.6        90.8
----------------------------------------------------------------------------
Average gold recovery (%)                       91.6        90.5        96.4
----------------------------------------------------------------------------
Silver produced (k oz)                         1,356       1,454       1,522
----------------------------------------------------------------------------
Gold produced (k oz)                           20.36       20.93       21.41
----------------------------------------------------------------------------
Silver sold (k oz)                             1,032       1,750       1,342
----------------------------------------------------------------------------
Gold sold (k oz)                               14.34       24.95       17.63
----------------------------------------------------------------------------
Co-product cash cost Au (US$)                    697         689         514
----------------------------------------------------------------------------
Co-product cash cost Ag (US$)                  13.90       13.10       11.70
----------------------------------------------------------------------------
----------------------------------------------------------------------------
(i)McEwen Mining holds a 49% attributable interest in the San Jose mine.


 

El Gallo Complex, Mexico (100%)

El Gallo Phase 1 construction is scheduled to be completed by mid-year. Capital costs to complete the project continue to be estimated at US$15 million. Key areas of advancement during the First Quarter include the crushing plant (60% complete), process plant (60% complete), and heap leach pad expansion (50% complete). Since December, 190,500 tonnes of material at an average grade of 1.29 gpt gold has been mined and stockpiled, totaling 7,900 ounces of gold. This represents approximately 2 months of production.

During the First Quarter, 14,000 meters of diamond drilling was completed at the El Gallo Complex. An updated resource estimate, which was scheduled for the end of April has been delayed by one month. The delay is primarily the result of high demand within the industry for resource contractors.

El Gallo Phase 1 is expected to produce 10,000 ounces of gold during the second half of 2012 and continue at 30,000 of gold per year after ramp-up. Once Phase 2 construction is completed during 2014, El Gallo is forecasted to produce approximately 5 million ounces of silver and 35,000 ounces of gold per year or 130,000 ounces of gold equivalent. (A photo library showing bi-weekly progress can be viewed by clicking here: http://mcewenmining.com/Media-Events/Gallerie...fault.aspx )

Gold Bar Project, Nevada (100%)

Gold Bar is forecasted to produce 50,000 ounces of gold per year at a cash cost of US$700 per ounce. The project is located on public lands managed by the Bureau of Land Management (BLM). The BLM and the Nevada Division of Environmental Protection will be the primary regulatory agencies responsible for approving the permit to mine.

McEwen Mining is advancing the permitting process by collecting baseline data in accordance with the BLM guidelines. It is expected that this phase will continue for at least 12 months.

Los Azules Copper Project, Argentina (100%)

Since January, a total of 2,850 meters of core drilling was completed at the Los Azules project, one of the world's largest undeveloped copper deposits. This was less than the originally estimated 8,000 meters. Difficult ground conditions not only slowed the pace of drilling but prevented many of the holes from reaching target depth. Results from the completed drill holes are currently being assayed and will be released in approximately 2 weeks.

In order to solve the problems encountered with the recent drilling at Los Azules, McEwen Mining signed a contract with Major Drilling to provide four core drills, which are considerably more powerful than the ones used this season. The company believes this will increase the likelihood of reaching target depths (+500 meters), where high-grade copper mineralization has been discovered. McEwen Mining anticipates starting the upcoming drill season in October, adding 3 months to the program and permitting a helicopter pad that would allow the drills to operate 12 months a year.

In addition, an updated resource estimate will be published by mid-year, which will incorporate the 7,350 meters of drilling completed in the current and previous seasons.

A portion of the Los Azules Copper Project is subject to litigation in the Courts of British Columbia. Shareholders and other interested parties are encouraged to review our most recent quarterly filings for detailed information. The trial is set to commence in November 2012 and last for approximately six weeks.

Santa Cruz Exploration, Argentina (100%)

During the First Quarter, a total of 2,950 meters of percussion drilling was completed on McEwen Mining's Celestina project near Anglo Ashanti's Cerro Vanguardia mine (annual production:230)(annual production:000 gold ounces - 0.9 million silver ounces). Through this exploration, a number of targets have been defined for core drilling. The Company plans to continue drilling into mid-May, prior the onset of Argentinian winter.

The drill permits for McEwen Mining's 100% owned claim package adjacent to the San Jose mine and Goldcorp's Cerro Negro project are in review with the provincial government. The Company has been notified that the earliest these permits could be approved would be by the end of the Second Quarter of 2012. The Company is planning to establish a drilling program to commence in the Third Quarter of 2012, which marks the beginning of Argentinian spring.

McEwen Mining Annual General Meeting

McEwen Mining Annual General Meeting will be held on May 17, 2012 at 4pm at the Wellington Ballroom of the Ritz-Carlton, located at 181 Wellington Street West, Toronto, Ontario, Canada, M5V 3G7.

This news release has been reviewed and approved by William Faust, P.E, McEwen Mining's Chief Operating Officer, who is a Qualified Person as defined by National Instrument 43-101.

About McEwen Mining ( www.mcewenmining.com )

The goal of McEwen Mining is to qualify for inclusion in the S&P 500 by 2015 by creating a high growth, low-cost, mid-tier silver and gold producer focused in the Americas. McEwen Mining's principal assets consist of the San Jose mine in Santa Cruz, Argentina (49% interest); the El Gallo Complex in Sinaloa, Mexico; the Gold Bar Project in Nevada, US; the Los Azules Project in San Juan, Argentina and a large portfolio of exploration properties in Argentina, Nevada and Mexico. In 2012, McEwen Mining is planning to spend approximately US$40 million on exploration.

McEwen Mining has 267,919,384 shares issued and outstanding. Rob McEwen, Chairman, President and CEO, owns 25% of the shares of the Company. As of March 31, 2012, McEwen Mining had cash and liquid assets of US$66.7 million, comprised of cash of US$41.1 million, silver and gold bullion at market value of US$21.4 million, short-term investments of US$3.1 million and marketable securities of US$1.1 million. The Company continues to hold a significant portion of its treasury in bullion with the belief that prices will continue to rise.

McEwen Mining Inc. (MUX) Stock Research Links

MUX Board Company Profile Buy Rating Time & Sales News Filings Financials
Scroll down for more posts ▼

Top 10 Most Recent News Articles

Top 5 Most Recently Viewed Articles

Next PR Unveils Cutting-Edge AI Optimization Solutions

Updated Category News Views 208

Next PR Launches Innovative AI Optimization Services Next PR, an award-winning public relations firm, has recently introduced its AI Optimization Services, aimed at helping brands maintain visibility and authority in today's AI-driven digital landscape. As companies strive to adapt to the ever-changing world of artificial intelligence and search engine results generated...

Continue Reading
Security and Vulnerability Management Market Set for Growth Surge

Updated Category News Views 144

Overview of the Security and Vulnerability Management Market The Security and Vulnerability Management Market is on an impressive trajectory, predicted to expand from USD 17.55 billion to USD 24.07 billion by 2030, reflecting significant growth propelled by rising global vulnerabilities. Market Growth Drivers Multiple factors are contributing to this market's growth....

Continue Reading
Bybit Unveils Groundbreaking MiCAR-Compliant Platform for Europe

Updated Category News Views 275

Introducing Bybit.eu: A New Era for European Crypto Users Bybit, a leader in the cryptocurrency exchange market and the world's second-largest by trading volume, is evolving by launching Bybit.eu. This fully MiCAR-compliant platform is crafted specifically for users across the European Economic Area (EEA). Bybit EU GmbH operates this platform as a licensed Crypto-Asset...

Continue Reading
Breakthrough Updates on NXP900 Clinical Development Journey

Updated Category News Views 128

Nuvectis Pharma Reports Significant NXP900 Findings Nuvectis Pharma, Inc. (NASDAQ: NVCT), known for its pioneering work in oncology, has shared key insights regarding NXP900 at a recent prestigious cancer research meeting. This innovative drug shows considerable promise in treating advanced cancers. Based on a Phase 1a dose-escalation study, NXP900 demonstrated strong...

Continue Reading
Elon Musk's Heartfelt Christmas Eve Adventure in Snowy Cold

Updated Category News Views 323

The Unexpected Christmas Quest of Elon Musk Christmas is a time when many cherish the joy of giving and receiving gifts. However, when you are someone like Elon Musk, a dynamic CEO known for pushing boundaries with Tesla and SpaceX, a forgotten gift can turn into an extraordinary adventure. Imagine waking on Christmas Eve only to realize that you forgot to buy your...

Continue Reading