SHAMARAN Q1 2016 FINANCIAL AND OPERATING RESULTS

May 19, 2016 - ShaMaran Petroleum Corp.  ("ShaMaran" or the "Company") (TSX VENTURE: SNM) (NASDAQ OMX: SNM) is pleased to announce its financial and operating results for the three months ended March 31, 2016. Unless otherwise stated all currency amounts indicated as “$” in this news release are expressed in thousands of United States dollars.

Construction of the 30,000 bopd Atrush Phase 1 Production Facility (“Production Facility”) is nearing mechanical completion. Commissioning is scheduled to begin in May of 2016. Completion of the production facilities is targeted for mid 2016.

Work on the dedicated feeder pipeline to be constructed between the Production Facility and the tie-in point on the main export pipeline has started.  The Atrush partnership is responsible for construction of the pipeline to the block boundary, which is progressing according to plan. The KRG is responsible for the construction of the section of the pipeline from the block boundary to the tie-in point on the main export pipeline. Originally it was planned to construct a 31 kilometre 12 inch pipeline from the block boundary to KCP2. It is now planned to construct a 12 inch pipeline to the location of a future blending station followed by a 36 inch pipeline. Delays in the commencement of this pipeline project have resulted in first oil being deferred until the fourth quarter of 2016.

The Operator plans to complete the Atrush-2 and Atrush-4 wells in June and July 2016. Four producing wells, all equipped with ESPs, will be available for production at start up.

Chris Bruijnzeels, President and CEO of ShaMaran, commented “Progress of the facilities construction is according to plan. Unfortunately, changes in the feeder pipeline scope outside the block boundary will result in a delay to first oil. However, the changed scope should result in increased flexibility of the KRG export pipeline system.”


FINANCIAL AND OPERATING RESULTS FOR THE THREE MONTHS ENDED MARCH 31, 2016

During the reporting period the Company continued its appraisal and development campaign in respect of the Atrush petroleum property located in the Kurdistan Region of Iraq which constitutes the continuing operations of the Company.  Atrush currently generates no revenues.

Financial Results

The Company reports a net loss of $2.8 million in the first quarter of 2016 which was primarily driven by routine general and administrative expenses and expensed borrowing costs on the Company’s senior secured bonds.

Condensed Interim Statement of Comprehensive Income

(Unaudited, expressed in thousands of United States Dollars)

      For the three months ended March 31,
        2016     2015
  Expenses from continuing operations              
Depreciation and amortisation expense       (11)     (16)
Share based payments expense       (76)     (676)
General and administrative expense       (1,302)     (963)
Loss before finance items and income tax expense       (1,389)     (1,655)
               
Finance income       21     542
Finance cost       (1,402)     (1,346)
Net finance cost       (1,381)     (804)
Loss before income tax expense       (2,770)     (2,459)
Income tax expense       (26)     (27)
Loss from continuing operations       (2,796)     (2,486)
Discontinued operations              
Net loss from discontinued operations       -     (10)
Loss for the period       (2,796)     (2,496)
               
Other comprehensive income              
Items that may be reclassified to profit or loss: Currency translation differences       32     11
Total other comprehensive income       32     11
               
Total comprehensive loss for the period       (2,764)     (2,485)

Condensed Interim Consolidated Balance Sheet

(Unaudited, expressed in thousands of United States Dollars)

    At March 31, 2016 At December 31, 2015
  Assets        
Non-current assets        
Property, plant and equipment     188,823 177,044
Intangible assets     89,477 88,645
      278,300 265,689
Current assets        
Cash and cash equivalents, unrestricted     18,411 30,409
Cash and cash equivalents, restricted     5,825 1,512
Other current assets     222 200
      24,458 32,121
Total assets     302,758 297,810
         
  Liabilities and equity        
Current liabilities        
Accounts payable and accrued expenses     11,956 9,560
Accrued interest expense on bonds     6,612 2,252
Current tax liabilities     16 31
      18,584 11,843
Non-current liabilities        
Borrowings     148,416 148,263
Provisions     8,822 8,080
      157,238 156,343
Total liabilities     175,822 168,186
Equity        
Share capital     593,179 593,179
Share based payments reserve     6,311 6,235
Cumulative translation adjustment     (51) (83)
Accumulated deficit     (472,503) (469,707)
Total equity     126,936 129,624
Total liabilities and equity     302,758 297,810

Total assets increased during the first quarter of 2016 by $4.9 million which corresponds to an increase in liabilities by $7.6 million mainly due to an increase in accounts payable, accrued expenses and accrued interest and a decrease in equity by $2.7 million principally due to the net loss recorded in the period.

Property, plant & equipment assets increased by $11.8 million during the first three months of 2016 was due to $9.0 million of Atrush development costs incurred during the period and capitalised borrowing costs of $2.8 million.  The increase in intangible assets by $0.8 million during the first quarter is due to $0.4 million of Atrush exploration costs incurred in the period and capitalised borrowing costs of $0.4 million.


Condensed Interim Consolidated Cash Flow Statement

(Unaudited, expressed in thousands of United States Dollars)

    For the three months ended March 31,
      2016     2015
 Operating activities            
 Net loss from continuing operations     (2,796)     (2,486)
 Adjustments for:            
Interest expense on senior secured bonds – net     1,335     1,336
Share based payments expense     76     676
Foreign exchange loss / (gain)     41     (479)
Unwinding discount on decommissioning provision     26     -
Depreciation and amortisation expense     11     16
Interest income     (21)     (63)
Changes in accounts payable and accrued expenses     2,396     (2,480)
Changes in provisions     -     (76)
Changes in current tax liabilities     (15)     (8)
Changes in other current assets     (22)     1,290
 Cash used in discontinued operations     -     (8)
 Net cash inflows from / (outflows to) operating activities     1,031     (2,282)
             
 Investing activities            
Interest received on cash deposits     21     63
Purchases of intangible assets     (361)     (16,324)
Purchase of property, plant and equipment     (8,365)     (1)
 Net cash outflows to investing activities     (8,705)     (16,262)
             
 Financing activities            
Shares issued on Rights Offering     -     60,462
Transaction costs on Rights Offering     -     (1,351)
 Net cash inflows from financing activities     -     59,111
             
Effect of exchange rate changes on cash and cash equivalents     (11)     487
             
 Change in cash and cash equivalents     (7,685)     41,054
 Cash and cash equivalents, beginning of the period     31,921     57,204
 Cash and cash equivalents, end of the period     24,236     98,258

The decrease by $7.7 million in the cash position of the Company during the first three months of 2016 was due to cash outflows of $8.7 million on Atrush Block development activities ,  $1.4 million of cash out on G&A and other cash expenses and $2.4 million of positive cash adjustments from changes in working capital items.

Operating Results

Production Facility and Export Pipeline 

  • Construction of the 30,000 bopd Atrush Phase 1 Production Facility (“Production Facility”) is nearing mechanical completion.  Commissioning is scheduled to begin in May of 2016. Completion of the production facilities is targeted for mid 2016.
  • Work on the dedicated feeder pipeline to be constructed between the Production Facility and the tie-in point on the main export pipeline has started.  The Atrush partnership is responsible for construction of the pipeline to the block boundary, which is progressing according to plan.  The KRG is responsible for the construction of the section of the pipeline from the block boundary to the tie-in point on the main export pipeline. It is now planned to construct a 12 inch pipeline to the location of a future blending station, followed by a 36 inch pipeline.  Delays in the commencement of this pipeline project have resulted in first oil being deferred until the fourth quarter of 2016.

Corporate Highlights

  • On February 15, 2016 the Company reported updates to estimated reserves and contingent resources for the Atrush block as of December 31, 2015. Total oil in place is estimated at 1.5 to 2.8 billion barrels, with Total Field Proven plus Probable (“2P”) Reserves on a property gross basis increasing from 61.5 million barrels (“MMbbl”) to 85.1 MMbbl, an increase of 38 percent. Total Field Unrisked Best Estimate Discovered Recoverable Resources (“2P + 2C”) 1  on a property gross basis increased from 372 million barrels oil equivalent (MMboe) 2  to 389 MMboe.
  • The Company closed a  financing arrangement in early May 2016 (the “Financing Arrangement”)  with holders of the $150 million bonds (the “Senior Bonds”) of General Exploration Partners. Inc. (“GEP”), a wholly owned subsidiary of ShaMaran. The Financing Arrangement provides the Company with additional liquidity in 2016 of approximately $33 million based on the issuance of $17 million of additional super senior bonds ($16.2 million proceeds net of transaction costs) and provides terms for the Company to pay bond coupon interest in kind by issuing additional bonds, including approximately $17.9 million of 2016 coupon interest. Also under the Financing Arrangement the Company issued 218,863,000 common shares at a deemed price of CAD 0.105 per share to holders of the Senior Bonds who elected to convert Senior Bonds into ShaMaran shares which represented $18 million of Senior Bonds at face value.

1. This estimate of remaining recoverable resources (unrisked) includes contingent resources that have not been adjusted for risk based on the chance of development. It is not an estimate of volumes that may be recovered.

2. Boe may be misleading, particularly if used in isolation. A boe conversion ratio of 6 million cubic feet (“Mcf”) per one barrel is based on an energy equivalency conversion method primarily applicable at the burner tip and does not represent a value equivalency at the wellhead.

 

OUTLOOK

The outlook for the remainder of the year 2016 is as follows:

Production Facility

Construction of the 30,000 bopd Atrush Phase 1 Production Facility will continue and commissioning is scheduled to be completed mid 2016.

Engineering and design of water injection facilities is planned to commence in 2016.

Oil Export Pipeline

Construction of the export pipeline has started. The scope of the pipeline has changed downstream of the Atrush Block boundary and it is now planned to consist of an 18 kilometre 12” section to the location of a future blending station and a 16 kilometre 36 inch section to the main export pipeline. First oil is now expected in the fourth quarter of 2016.


Wells

The Operator plans to complete the AT-2 and AT-4 wells prior to first production. Four producers, all equipped with ESPs, are planned to be available for production at start up.

This will be followed by the drilling and completion of a dedicated water disposal well and the drilling of an appraisal and development well in 2017.

ANNUAL GENERAL MEETING

The Company also announces that the Annual General Meeting of Shareholders will be held on Wednesday, June 15, 2016, at 8:00 a.m. (Vancouver time) at Suite 2000, 885 West Georgia Street, Vancouver, British Columbia, V6C 3E8.

     

ABOUT SHAMARAN

ShaMaran Petroleum Corp. is a Kurdistan focused oil development and exploration company with a 26.8% direct interest in the Atrush oil discovery until such time that the Kurdistan Regional Government has completed the exercise of its right to acquire up to a 25% interest. The Atrush Block is currently undergoing an appraisal and development campaign.

ShaMaran is a Canadian oil and gas company listed on the TSX Venture Exchange and the NASDAQ OMX First North Exchange (Stockholm) under the symbol "SNM". Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release. Pareto Securities AB is the Company’s Certified Advisor on NASDAQ OMX First North.

The Company's condensed interim consolidated financial statements, notes to the financial statements and management's discussion and analysis have been filed on SEDAR ( www.sedar.com ) and are also available on the Company's website ( www.shamaranpetroleum.com ).

FORWARD LOOKING STATEMENTS

This news   release contains statements and information about expected or anticipated future events and financial results that are forward-looking in nature and, as a result, are subject to certain risks and uncertainties, such as legal and political risk, civil unrest, general economic, market and business conditions, the regulatory process and actions, technical issues, new legislation, competitive and general economic factors and conditions, the uncertainties resulting from potential delays or changes in plans, the occurrence of unexpected events and management’s capacity to execute and implement its future plans.  Any statements that are contained in this news release that are not statements of historical fact may be deemed to be forward-looking information. Forward-looking information typically contains statements with words such as   "may", "will", "should", "expect", "intend", "plan", "anticipate", "believe", "estimate", "projects", "potential", "scheduled", "forecast", "outlook", "budget" or the negative of those terms  or similar words suggesting future outcomes. The Company cautions readers regarding the  reliance placed by them on forward‐looking information as by its nature, it is based on current expectations regarding future events that involve a number of assumptions, inherent risks and uncertainties, which could cause actual results to differ materially from those anticipated by the Company.  

Actual results may differ materially from those projected by management. Further, any forward-looking information is made only as of a certain date and the Company undertakes no obligation to update any forward-looking information or statements to reflect events or circumstances after the date on which such statement is made or reflect the occurrence of unanticipated events, except as may be required by applicable securities laws. New factors emerge from time to time, and it is not possible for management of the Company to predict all of these factors and to assess in advance the impact of each such factor on the Company’s business or the extent to which any factor, or combination of factors, may cause actual results to differ materially from those contained in any forward-looking information.

---

For the complete report see attached file.

         FOR FURTHER INFORMATION PLEASE CONTACT:                    Chris Bruijnzeels          President and CEO          ShaMaran Petroleum Corp.          +41 22 560 8605          chris.bruijnzeels@shamaranpetroleum.com                    Sophia Shane          Corporate Development          ShaMaran Petroleum Corp.          +1 604 689 7842          sophias@namdo.com          www.shamaranpetroleum.com                    Robert Eriksson          Investor Relations, Sweden          ShaMaran Petroleum Corp.          +46 701 112615          reriksson@rive6.ch

Scroll down for more posts ▼

Top 10 Most Recent News Articles

Build-A-Bear Lawsuit Puts Guidance Under a Microscope

Updated Category News Views 48

A stuffed-animal retailer is not supposed to leave investors parsing legal pleadings, yet BBW holders now have exactly that chore. A securities class action announced November 23 alleges that Build-A-Bear Workshop made materially false and misleading statements during a relatively tight window: May 28, 2026 through August 26, 2026. This is not a court ruling, not proof of...

Continue Reading
CARsgen's CT1182 Data Opens a Careful New CAR-T Test

Updated Category News Views 323

Six very sick lymphoma patients are not a victory lap, but they can still make the whole cell-therapy field sit up straighter. CARsgen has disclosed first clinical results for CT1182, an in vivo CAR-T candidate built on its CARvivo platform, and the early package is plainly more interesting than the usual preclinical chest-thumping. The company reported three complete...

Continue Reading
MetaOptics Gets a S$32 Million Flexible Capital Backstop

Updated Category News Views 143

A semiconductor optics outfit just bought itself some breathing room, not a blank cheque. MetaOptics has signed a proposed share subscription facility with GEM Opportunities Fund ISA Ltd. worth up to S$32 million, a potentially meaningful capital backstop for a company trying to keep daily operations moving while pursuing a new U.S. fabrication line. Flexibility Has...

Continue Reading
Harel's Record Core Profit Has a Market-Return Catch

Updated Category News Views 124

A billion-shekel profit headline can make an insurer look bulletproof until the market ledger starts arguing back. Harel Insurance Investments delivered a muscular third quarter on the operating side, with underwriting, asset management and credit all moving in the right direction. Yet reported comprehensive income took a hard step down because the company's own...

Continue Reading
AADX Probe Puts Supply and Margin Claims Under Lens

Updated Category News Views 152

Three Operational Snags, One Nasty Market Reaction Rotor heads, component shortages, and ugly ramp costs are not the sort of words investors want clustered around a defense supplier after they own the stock. Applied Aerospace & Defense is now the subject of an investigation announced by shareholder-rights law firm Schall, Brown & Schwartz LLP, which is examining whether...

Continue Reading
LG's Windshield Display Award Signals Auto Tech Push

Updated Category News Views 232

A windshield has become the latest patch of contested automotive real estate. LG Electronics picked up a 2026 Automotive News PACE Pilot Award for its UltraView Windshield Display, and the prize is a respectable nod to the idea. Still, nobody should confuse a pilot-stage trophy with a production contract. Automotive hardware has humbled plenty of clever companies after...

Continue Reading
Cardiovalve's Three-Year Data Clears a Crucial EU Hurdle

Updated Category News Views 304

A failing tricuspid valve is not a spreadsheet problem, and that matters before anybody gets carried away with a glossy conference presentation. Venus Medtech's Cardiovalve unit has reported results from TARGET in a population that was old, sick and largely out of good surgical options. That is precisely where a less invasive replacement therapy has to prove it can do...

Continue Reading
Fervo Lawsuit Puts IPO Claims Under a Harder Light

Updated Category News Views 133

Geothermal stories sell patience; a securities complaint is what arrives when patience starts getting expensive. Fervo Energy Company is facing a proposed federal securities class action tied to its May 13, 2026 initial public offering, and the allegations go straight at two things investors should have been measuring with a ruler: pilot-plant thermal performance and...

Continue Reading
Coprod’s $6M Pre-Seed Tests Modular Robot Hardware

Updated Category News Views 44

Robot hardware has spent far too long behaving like a bespoke plumbing emergency. Every new machine needs motors, sensors, batteries, controls, mechanical fit, software links, safety work, and somebody capable of making the whole unruly pile cooperate. Swiss startup coprod is pitching a cleaner answer: modular components plus a shared software layer, funded by a $6...

Continue Reading
Global Child Tests Purpose Travel's Expanding Media Reach

Updated Category News Views 324

Celebrity travel programming usually melts into the wallpaper, but Global Child is trying to make the scenery answer for itself. Its new season of Global Child “Travel & Purpose” puts Andrea Bocelli in Tuscany, Isabela Merced in Peru and John Malkovich in Croatia, while tying each destination to a broader local-good mission. That is a more thoughtful pitch than...

Continue Reading

Top 5 Most Recently Viewed Articles

Ed Yardeni's Optimistic Outlook for Future Stock Growth

Updated Category News Views 248

Ed Yardeni, the Wall Street strategist known for his sunny outlook, predicted back in 2024 that the S&P 500 could skyrocket to 8,000 by 2030. Traders perked up at this bold claim, as it wasn't just wishful thinking; it was backed by an understanding of compound interest—one of finance’s most powerful growth engines. Breaking Down Yardeni's Projections: Are They...

Continue Reading
TopBuild's Investor Day 2025: Insightful Strategies and Growth

Updated Category News Views 214

TopBuild's Investor Day: A Glimpse into the Future TopBuild Corp., a premier installer of insulation and commercial roofing, is excited to host its Investor Day today, featuring a robust lineup of presentations and discussions aimed at demonstrating its strategic vision. Attendees can look forward to sessions led by President and CEO Robert Buck, alongside CFO Rob Kuhns...

Continue Reading
ZOOZ Power Expands EV Charging Solutions in China's Market

Updated Category News Views 184

ZOOZ Power's Strategic Move into the Chinese EV Market ZOOZ Power Ltd. (NASDAQ: ZOOZ, TASE: ZOOZ), renowned for its cutting-edge flywheel-based power-boosting technology, has marked a significant milestone by sending its first boosting system, the ZOOZTER-100, to China. This is a crucial step for the company as it endeavors to integrate into the largest electric vehicle...

Continue Reading
Verkada Enhances Security Solutions with SimonsVoss Partnership

Updated Category News Views 231

Verkada Enhances Security Solutions with SimonsVoss Partnership Verkada, a leader in cloud-based physical security, has unveiled a new integration with SimonsVoss wireless locks during the VerkadaOne London conference in front of over 400 IT and security professionals. This partnership marks a significant step forward for Verkada as they aim to improve access control...

Continue Reading
Investors Urged to Act in Rocket Lab Class Action Case

Updated Category News Views 397

Investors Advised on Rocket Lab Class Action Lawsuit Faruqi & Faruqi, LLP, a prominent national securities law firm, is reaching out to investors who have experienced substantial losses in Rocket Lab USA, Inc. This law firm, known for its advocacy in securities litigation, emphasizes the importance of acting swiftly for those affected. The firm is currently assisting...

Continue Reading