Dear Customer, This IT Notice includes instructions for mandatory activities for ALL GCF and FDS customers and service providers with connectivity to Nasdaq Nordic and Nasdaq Baltic.
This data center relocation requires that all GCF customers make necessary arrangements in order to establish connectivity to the new VASBY data center. If not yet done, please contact your connectivity provider as soon as possible to make sure you have connectivity to the VASBY data center in advance of the mandatory tests described further down in this notice. If you are only using FDS please see the details below. We have just published a new monthly newsletter with general information about the Data Center relocation project.
A. GCF relocation details
A.1 Systems
New GCF pre-production system in Vasby will receive the production status on May 23, 2016. Old production system in Lunda will be used till May 22, 2016. Pre-production system will be running release GCF 3.1 till April 22, 2016, thereafter the release is 3.2. The pre-production system will be the main test system till May 23, 2016 . It will also be used for mandatory tests (please see the details below). Nasdaq will also provide 4 new external GCF test systems in Vasby named TST1, TST2, TST3 and TST4. New test systems will be used on parallel with the old GCF test systems till May 23, 2016, after which old (EXT) systems will seize to exist. Implementation schedule:
- Pre-production system becomes accessible March 29, 2016
- TST4 April 18, 2016
- TST1, TST2 and TST3 May 2, 2016
A.2 Connectivity to Vasby systems
Usernames and passwords for GCF pre-production will have a prefix “X”. Those will also be sent directly to named GCF contacts via email during this week. Subscriptions in pre-production will be similar to current production. Usernames and password for TST 1-4 will be the same ones as for current EXT 1-4; also the subscriptions will be the same. Other connectivity details (IPs and ports) are available in GCF Connectivity Guideline Document . Related to network, please contact your connectivity provider for more information.
A.3 Sources
Source systems connected to Vasby GCF sites will be informed on GCF and Data Center Relocation web sites.
A.4 GCF testing
All the environments can be used for login verifications, but failover testing and all mandatory testing must be done in pre-production environment.
Mandatory test
- Must be performed successfully at least once in pre-production between April 11 – April 28, 2016
- Expected verifications: successful login and failover
- Reporting (email) to dataproducts@nasdaq.com
Forced failover takes place in pre-production between Mon-Thu at 14:00 CET till May 22, 2016.
B. FDS relocation details
B.1 Systems
There will be a new FDS test area connected to each new GCF system in Vasby, also GCF pre-production.
FDS production in Vasby begins along with the GCF launch on May 23, 2016, and implementation of FDS test areas follow the schedule of the GCF test systems (TST1-4) those are connected to.
FDS changes will be mainly transparent and those customers using only production FDS don’t have to change anything. However, we recommend customers connecting the FDS via other channels than open internet to verify their connectivity.
Same test user credentials are valid in each FDS test area. Annual FDS production password changes will be done in August/September, not in May as usual.
B.2 Testing FDS test area name for the instance connected to GCF pre-production will have a name “PREPROD”. Sample URL:
https://<username>:<password>@fdstest01.nasdaqomxnordic.com/ preprod /today/ FDS test area names for the instances connected to new GCF test sites will have corresponding area names, for example area connected to GCF TST1 will have a name “TST1”. Sample URL: https://<username>:<password>@fdstest01.nasdaqomxnordic.com/ tst1 /today/
Further information is available on Data Center Relocation web pages .
If you have any questions please contact dataproducts@nasdaq.com