$WOGI-SA- Power Plant Projects Project # 2- Ou
Post# of 8672
Project # 2- Outside Lima
Location Near Lima (see map)
Installed capacity 6.5 MW
Tunnel 1.4 Kms / Channel length 0.5 Km
Capacity factor 64.7%
Expected yearly production 50.7 GWh
Hydrology studied over 36 years
Project data reviewed and verified by Lombardi SPA
Studies available upon request for detailed due diligence (an executed NDA is required)
Expected returns 17.7 %IRR
Renewable PPA for 15 years
TOTAL EST. COST USD 12.4 Million (EPC estimated cost USD 11 Million)
Construction period 15 months
http://stockpumpers.blogspot.com/2015/10/worl...igned.html