Highbank Res Ltd (HBKRF) 0.2706 $HBKRF
Highbank Swamp Point North Barge Loading Facility Update
Marketwire Canada - Mon Sep 22, 4:00AM CDT
Highbank Resources Ltd. (the "Company"

(TSX VENTURE: HBK) (FRANKFURT: V7O). Further to our September 15, 2014 news release, the Company would like to update the progress of our load out facility. Transportation of the pilings to the Port of Prince Rupert was delayed by a labour action at the docks in Vancouver. We are now pleased to be able to report that the pilings are now in Prince Rupert, and loading onto Foresight Innovations, pile driving barge. Crews have welded together pilings of required length to form the initial moorings for the Swamp Point North Barge Loading Facility. The barge is expected to leave the Port of Prince Rupert today. The addition of Foresight's crew will bring the total site construction workforce to 14. It should be noted that the load-out facility will be incorporated on future nautical charts of the area when completed.
Highbank Ships Crusher and Wash Plant to Swamp Point North
Marketwire Canada - Mon Sep 15, 3:00AM CDT
Highbank Resources Ltd. (the "Company"

(TSX VENTURE: HBK) (FRANKFURT: V7O), is pleased to announce that the crusher, wash plant and all associated equipment arrived on site during the weekend. In addition a larger excavator was shipped to accelerate the site preparation. With this equipment installed, work can commence on the production of aggregate stockpiles in preparation for shipping. This approach will increase timely shipping of aggregate, once the load out system has been installed. Pilings are currently in Surrey (Vancouver) and will have priority loading and trucking to Prince Rupert. Barging to the site will take place later this week.
Highbank Receives Amended Mines Act Permit on Its Swamp Point North Aggregate Project
Marketwire Canada - Thu Sep 04, 4:00AM CDT
Highbank Resources Ltd. (TSX VENTURE: HBK)(FRANKFURT: V7O), (the "Company"

. Further to our news release dated March 26, 2014, Highbank is pleased to announce receipt of our Mines Act Permit which authorizes sand and gravel (aggregate) extraction activities as detailed in the Notice of Work and Reclamation Program ("NoW"

dated October 31, 2013.
Collins Barrow partner joins BC mining company board
CNW Group - Thu Aug 28, 8:00AM CDT
The Managing Partner of our Chatham-Kent office, Collins Barrow's Bill Loucks, CPA, CA, CFP, has been appointed to the board of Highbank Resources Ltd. (TSX.V:HBK) of British Columbia, an aggregate exploration and development company. In addition to overseeing Chatham consulting services, Mr. Loucks brings more than 20 years of experience to the role as a former long-serving director of Collins Barrow's National Board and of Chatham-Kent Hydro Inc.
Highbank Finalizes Barge Load-Out and Piling Construction Contract
Marketwire Canada - Wed Aug 20, 8:00AM CDT
Highbank Resources Ltd. (TSX VENTURE: HBK) (the "Company"

is pleased to announce that a contract has been finalized with Foresight Innovations Ltd. ("Foresight"

of Victoria, B.C.
Highbank Appoints William (Bill) Loucks, CPA, CA, CFP, to the Board of Directors
Marketwire Canada - Mon Aug 11, 8:00AM CDT
Highbank Resources Ltd. (TSX VENTURE: HBK) (FRANKFURT: V7O),(the "Company"

is pleased to announce the appointment of Mr. William (Bill) Loucks, CPA, CA, CFP, to the Board of Directors.
Highbank Closes 2nd Tranche - $1.3 Million Convertible Debenture and Swamp Point North Progress Update
Marketwire - Fri Aug 08, 8:01AM CDT
NOT FOR DISTRIBUTION TO UNITED STATES NEWSWIRE SERVICES OR FOR DISSEMINATION IN THE UNITED STATES
Highbank Continues Mobilization & Site Development at Swamp Point North
Marketwire - Thu Jul 24, 8:02AM CDT
Highbank Resources Ltd. (TSX VENTURE: HBK) (FRANKFURT: V7O), (the "Company"

.
Highbank Is Proceeding to Close the 2nd Tranche of $1.3 Million Convertible Debenture Financing
Marketwire Canada - Fri Jul 18, 3:33PM CDT
Highbank Resources Ltd. (TSX VENTURE: HBK) (FRANKFURT: V7O) (the "Company"

-- Mr. Gary Musil, CFO, is pleased to announce that the Company is proceeding with the closing of the 2nd tranche of $1.3 million of our total $4 million convertible debenture financing, and have expressions of interest for an additional $500,000. The Company closed the 1st tranche of $2.7 million on April 15/14.
Highbank Mobilizes and Commences Site Development at Swamp Point North
Marketwire - Thu Jun 26, 9:17AM CDT
Highbank Resources Ltd. (TSX VENTURE: HBK)(FRANKFURT: V7O), (the "Company"

.
Highbank Signs Tug & Barging Letter of Intent and Completes 'OLTC' Timber Assessment
Marketwire - Thu Mar 27, 8:04AM CDT
Highbank Resources Ltd. (TSX VENTURE: HBK)(FRANKFURT: V7O) (the "Company" or "Highbank"

is pleased to announce:
Highbank Receives Mines Act Permit on Its Swamp Point North Aggregate Project
Marketwire - Wed Mar 26, 8:05AM CDT
Highbank Resources Ltd. (TSX VENTURE: HBK)(FRANKFURT: V7O) (the "Company" or "Highbank"

. Further to our news release dated March 19, 2014, Highbank is extremely pleased to announce receipt of the Mines Act Permit which authorizes sand and gravel extraction activities as detailed in the Notice of Work and Reclamation Program ("NoW"

dated October 31, 2013.
Highbank Signs Letter of Intent for Increased Aggregate Commitment With North Coast Concrete
Marketwire - Tue Mar 25, 8:05AM CDT
Highbank Resources Ltd. (the "Company" or "Highbank"

(TSX VENTURE: HBK)(FRANKFURT: V7O) is pleased to announce that the Company has signed a Letter of Intent ("LOI"

with North Coast Concrete of Prince Rupert. North Coast Concrete has committed to accept 150,000 tons of aggregate based on the ability of Highbank to meet the specifications and delivery requirements as stipulated, for use in concrete to supply construction projects in the Port of Prince Rupert and area, for one year from the date of the LOI.
IIROC Trade Resumption - Highbank Resources Ltd.
Newsfile Corp - Wed Mar 19, 8:12AM CDT
Trading resumes in:
Highbank Receives Notice of Work Permit Approval on Its Swamp Point North Aggregate Project
Marketwire - Wed Mar 19, 7:03AM CDT
Highbank Resources Ltd. (TSX VENTURE: HBK)(FRANKFURT: V7O) (the "Company" or "Highbank"

is very pleased to announce that the Company has received the Notice of Work ("NoW"

Permit approval and a 'Reclamation Security Request for the Swamp Point North Aggregate Project'. Based on the information Highbank has provided as reviewed by the Ministry of Energy and Mines ("MEM"

, and referral comments received from other government agencies and First Nations regarding the Notice of Work and Reclamation Program application ("NoW"

dated October 31, 2013, the MEM is ready to issue a new Mines Act Permit.