El Gallo Complex development update.
Phase 1 construction at the El Gallo Complex remains within budget and on schedule for first gold pour expected mid-year, 2012!
Key development highlights over the past two weeks are:
- To date: 63,700 tonnes of material averaging 1.71 gpt gold has been stockpiled
- Crushing plant now 50% complete
- Process plant is 40% complete
- Heap leach pad expansion 35% complete
New Photos
http://media3.marketwire.com/docs/McEwan0316.pdf