Just a update, I just left the site, there was no workers on site today((saturday) but the fence is coming along well, IMO it appears the pole installation is 90%. the north side is complete, the west side is complete other than where the house sits, the east side is about 75% complete and the south side has the pole in except for the driveway leading to the exsisting main building. There has been more foundation poured on the east side, and the foundation that was poured last week is now insulated and back filled, sorry there is not pics, but I am old school and not very computer savvy.