Robex Resources Advances Kiniero Gold Project to 2025 Milestone

Progress Update on Robex Resources Kiniero Gold Project
Highlights:
- Robex Resources is executing its construction plan at the Kiniero Gold Project successfully. The company is on track for the initial gold pour scheduled for Q4 2025.
- The project site has maintained an excellent safety record, free from lost time injuries.
- Recently, the phase 1 contract for grade control drilling has been awarded and the drilling is now underway.
- A contract for the construction of the structural, mechanical, and piping necessary for the process plant was awarded, with the contractor expected to mobilize in May 2025.
- The engineering and detailed design of the process plant have been completed.
- The first four engines and generators for the power station are nearing completion with testing planned at Hyundai’s factory.
- Key mechanical and electrical equipment orders have been placed, including CIL agitators, a pebble crusher, and conveyor drives.
- Construction of the primary crusher ROM wall has been finalized, and backfilling of the ROM pad has started.
- Concrete foundations for the SAG and ball mills have been fully completed, ensuring a solid base for future operations.
- Structural steel and platework fabrication is currently 55% complete, with multiple shipments already in transit to the Kiniero site.
- Progress on concrete work for the process plant is on schedule, having poured 85% of the planned 7,065m³ of concrete so far.
- Tank structures are well underway, with completion of the first six tanks at full height for the CIL Train A circuit.
- Preparation for the tailings storage facility is advancing, with lining work well underway, exceeding 90,000m² of liner laid down in recent weeks.
QUEBEC CITY, April 02, 2025 -- Robex Resources Inc. (“Robex”), a West African gold producer, is excited to share the current status of its Kiniero Gold Project construction. The company anticipates that the first gold will be produced in Q4 2025, followed by projections of 155,000 ounces of gold production in 2026.
Construction Overview and Responsibilities
Robex’s Managing Director and CEO, Matthew Wilcox, expressed his enthusiasm regarding the ongoing developments, stating, “Kiniero is proceeding according to plan, and we remain confident in achieving our target for gold production by Q4 2025. The sight of this project advancing with our teams working safely and collaboratively is invigorating. As construction progresses, we focus on achieving our goals consistently.”
The construction schedule is robust, having witnessed the completion of the SAG and ball mill foundations recently. Additionally, work on the primary crusher ROM wall is now finished, with backfilling processes in progress. Tailings storage facility lining has begun, and concrete work for the power station is in full swing.
Future Steps and Tasks Ahead
- Awarding of significant contracts for mill installations, mining operations, haulage, as well as drilling and blasting activities.
- Commencing the design phase for a solar farm to enhance sustainability.
- Start of mobilization for the SMP contractor by the second quarter of 2025.
- Mobilization of the mining contractor targeted for the third quarter of 2025.
Robex is strategically positioned to continue advancing the Kiniero Gold Project while adhering to its timeline, ensuring that first gold production is realized by Q4 2025. The expectation remains firm regarding achieving 155,000 ounces of gold output in 2026.
Contact Information for Further Inquiries
ROBEX RESOURCES INC.
Matthew Wilcox, Chief Executive Officer
Alain William, Chief Financial Officer
Phone: +1 581 741-7421
Email: investor@robexgold.com
Website: www.robexgold.com
Frequently Asked Questions
What is the projected timeline for first gold production at Kiniero?
The first gold pour is scheduled for Q4 2025, with plans to ramp up production subsequently.
How much gold is Robex expecting to produce in 2026?
Robex anticipates producing approximately 155,000 ounces of gold at Kiniero in 2026.
What construction updates have been reported for the Kiniero Gold Project?
Key updates include completion of the SAG and ball mill foundations, as well as ongoing concrete work and lining of the tailings storage facility.
Who is leading the project development at Robex?
Matthew Wilcox serves as the Managing Director and CEO, overseeing the project’s progress and strategic direction.
Where can I get more information about Robex and its projects?
Additional information can be found on Robex's website at www.robexgold.com.
About The Author
Contact Evelyn Baker privately here. Or send an email with ATTN: Evelyn Baker as the subject to contact@investorshangout.com.
About Investors Hangout
Investors Hangout is a leading online stock forum for financial discussion and learning, offering a wide range of free tools and resources. It draws in traders of all levels, who exchange market knowledge, investigate trading tactics, and keep an eye on industry developments in real time. Featuring financial articles, stock message boards, quotes, charts, company profiles, and live news updates. Through cooperative learning and a wealth of informational resources, it helps users from novices creating their first portfolios to experts honing their techniques. Join Investors Hangout today: https://investorshangout.com/
The content of this article is based on factual, publicly available information and does not represent legal, financial, or investment advice. Investors Hangout does not offer financial advice, and the author is not a licensed financial advisor. Consult a qualified advisor before making any financial or investment decisions based on this article. This article should not be considered advice to purchase, sell, or hold any securities or other investments. If any of the material provided here is inaccurate, please contact us for corrections.