Processor #3 – The assembly of the third processor is nearing completion at our Niagara Falls facility. Highlights of the progress include:
All kilns and towers are in place;
Erection of the emission stack is nearly complete;
50,000 gallons of new fuel storage tanks are in place and connected;
Two new loading docks are in place to enable increased material handling of feedstock;
Testing of all subsystems is expected to begin shortly.
page 23 of the 10Q - pdf