Exciting Developments at the Kiniéro Gold Project
Robex Resources Inc., a prominent West African gold producer, is thrilled to share the latest updates on the Kiniéro Gold Project. With each passing month, Robex is gearing up for its first gold production, targeted for the fourth quarter.
Milestones Achieved in Project Construction
The commissioning and operations team are fully mobilized on-site, indicating that work is progressing swiftly at the Kiniéro Gold Project. Recently, the first ore was delivered to the Run-of-Mine (ROM) pad, signaling the imminent start of production. The mining contractor's fleet is nearing completion, ready to move into the next phase of operation.
Key Enhancements in Infrastructure
Significant progress has also been made in terms of infrastructure, including the near-completion of the tailing storage facility, poised to support the ore commissioning in the process plant. Moreover, the installation and testing of the power station engines have been successfully accomplished, ensuring the site is electrically ready for energization.
The Importance of Grade Control
Robex has completed grade control drilling over the Sabali pit, a crucial step that aids in the effective management of materials as production begins. This proactive measure ensures that they can optimize the extraction processes, reflecting their commitment to operational excellence.
Process Plant Preparations Underway
As we move forward, the pre-commissioning of the high voltage switchgear has been completed, preparing it for testing with energization planned shortly. Electrical and pre-commissioning activities for the process plant are ongoing, aligning with the priority activities set for commissioning.
Communication Networks Established
The communication network within the process plant has been successfully installed and connected to the control system, ensuring seamless operations. Meanwhile, functional testing of the CIL motor control center has commenced, helping to advance project timelines significantly.
Words from the Leadership Team
Matthew Wilcox, the Managing Director and Chief Executive Officer of Robex, expressed his enthusiasm regarding the ongoing project advancements, stating, "It is gratifying to witness the consistent progress at Kiniéro. Our project remains on track for achieving first gold production this year." He further elaborated that grade control drilling is complete, and the team is fully funded and on budget for the project's completion.
Looking Ahead: Path to First Gold
As the commissioning phase progresses, Robex remains committed to completing construction at the Kiniéro Gold Project, which is on schedule to realize first gold production within the next quarter. This milestone is pivotal for the company's growth and will significantly enhance its operational portfolio.
Contact Information
If you wish to know more about the Kiniéro Gold Project or have any inquiries, please reach out to:
Robex Resources Inc.
Matthew Wilcox, Managing Director and CEO
Alain William, Chief Financial Officer
Email: investor@robexgold.com
Website: www.robexgold.com
Frequently Asked Questions
What are the current advancements at the Kiniéro Gold Project?
The commissioning team is fully operational, with significant infrastructure enhancements and the delivery of first ore to the ROM pad.
What is the expected timeline for first gold production?
Robex Resources aims for first gold production in the fourth quarter.
Who is leading the initiatives at Robex Resources?
Matthew Wilcox serves as the Managing Director and CEO, guiding the company through these developments.
How is Robex executing its construction plans?
The project is on schedule, fully funded, and progressing in a safe and methodical manner.
Where can I find updates about Robex Resources?
For continuous updates, stakeholders can refer to Robex's official website and investor relations communications.